Energy Projects Near You

Renewable energy projects in Winchester

41 solar, wind or battery projects of 150 kW or more are located in Winchester (REPD, July 2026 extract): 5 pending, 20 approved but not running, 8 operational and 1 refused. The council refused 4 of 37 decided applications (11%; UK 19%), with a median 15 weeks from submission to decision.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

41projects in the council area
5awaiting a decision
20approved, not running
11%of decisions refused

How Winchester decides

ApplicationsWinchesterUK
Decided applications (solar, wind, battery)3710,236
Refused4 (11%)19%
Solar refused0 of 2412%
Onshore wind refused3 of 345%
Battery storage refused1 of 1016%
Median time from submission to decision14.7 weeks17.0 weeks
Appeals lodged / allowed3 / 0—

Projects in Winchester

Projects of 1 MW and more (27)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updated
Silkstead Farm, Poles Lanebattery storagebattery storage49.9approved, not builtupdated Dec 2025Jun 2024granted Mar 2025Dec 2025
Titchfield Lane, Wickhamsolar farmsolar farm49.9approved, not builtupdated Nov 2025Feb 2025granted Sep 2025Nov 2025
Titchfield Lanebattery storagebattery storage49under constructionupdated Aug 2023Dec 2019granted Aug 2020Aug 2023
Southwick Estatesolar farmsolar farm48operationalupdated Mar 2015Oct 2013granted Dec 2013Mar 2015
Three Maids Hill Solar Farmsolar farmsolar farm25operationalupdated Jan 2024Oct 2020granted May 2021Jan 2024
South Lynch Farm Solar Farmsolar farmsolar farm20approved, not builtupdated Feb 2026Apr 2023granted Oct 2024Feb 2026
Winchester Battery Storagebattery storagebattery storage19operationalupdated Mar 2026Apr 2017granted Jun 2017Mar 2026
New Farm House Locks Farmsolar farmsolar farm18approved, not built may be out of dateupdated Oct 2024Jun 2021granted Jun 2023Oct 2024
Ash Farm, Titchfield Lanebattery storagebattery storage15approved, not builtupdated Mar 2025May 2023granted Feb 2025Mar 2025
Bullington Cross Wind Farm (7 of 14 turbines Winchester City Council)wind farmwind farm14appeal withdrawnupdated Jul 2015Apr 2013refused Jun 2014Jul 2015
Bishops Suttonsolar farmsolar farm12operationalupdated Oct 2014Sep 2013granted Nov 2013Oct 2014
Bishop’s Waltham Solar Farmsolar farmsolar farm12operationalupdated May 2017Apr 2015granted Aug 2015May 2017
Godsfield Solar Farmsolar farmsolar farm11.8application withdrawnupdated May 2022Jan 2021—May 2022
Funtley Solar Photovoltaic PV Farmsolar farmsolar farm10.5application submittedupdated Oct 2024Sep 2024—Oct 2024
Funtley Refuse Tipsolar farmsolar farm10permission expiredupdated Sep 2017Jun 2013granted Aug 2013Sep 2017
Fontley House Farmsolar farmsolar farm10approved, not built may be out of dateupdated Aug 2020Apr 2016granted May 2017Aug 2020
Stockbridge Roadbattery storagebattery storage10approved, not built may be out of dateupdated Feb 2020Oct 2017granted Dec 2017Feb 2020
Glebe Farm, Curdridge Lane Solar Farmsolar farmsolar farm10application submittedupdated Jul 2025May 2025—Jul 2025
Bullington Cross Wind Farm (Basingstoke and Deane)wind farmwind farm8appeal withdrawnupdated Jul 2015Apr 2013refused Jun 2014Jul 2015
Field House Solar / Hursley Roadsolar farmsolar farm6.4operationalupdated Sep 2018Apr 2014granted Jul 2014Sep 2018
Bullington Cross Wind Farm (3 of 14 turbines Test Valley BC)wind farmwind farm6appeal withdrawnupdated Jul 2015Apr 2013refused Jun 2014Jul 2015
Raglington Farmsolar farmsolar farm5.8operationalupdated Jul 2018Apr 2012granted Jul 2012Jul 2018
Western Court, Bishops Sutton Road Solar Farmsolar farmsolar farm5.4application submittedMar 2026——
Home Farm, Hursley Park Roadsolar farmsolar farm5approved, not builtupdated Jul 2025Oct 2024granted Jun 2025Jul 2025
Forest Farmsolar farmsolar farm3operationalupdated May 2017Feb 2015granted Dec 2015May 2017
Sparsholt collegebattery storagebattery storage2permission expiredupdated Aug 2020Sep 2017granted Dec 2017Aug 2020
IBM Hursleybattery storagebattery storage1.5approved, not builtupdated Jul 2024Mar 2024granted Jun 2024Jul 2024
Smaller schemes under 1 MW, mostly rooftop solar (14)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updated
CooperVision, Concorde Way - Unit 8 - Solar Panelsrooftop solarrooftop solar0.9approved, not builtupdated Jun 2025Apr 2025granted Jun 2025Jun 2025
Sainsburys Supermarkets, Badger Farm Roadrooftop solarrooftop solar0.6approved, not builtupdated Jun 2024May 2024granted Jun 2024Jun 2024
Octagon House, Concorde Wayrooftop solarrooftop solar0.4approved, not builtupdated Dec 2023Nov 2023granted Dec 2023Dec 2023
Fusion, Parkwayrooftop solarrooftop solar0.2approved, not builtupdated Jul 2023May 2023granted Jul 2023Jul 2023
Pet Centre Garsons Garden Centre, Fontley Roadrooftop solarrooftop solar0.2approved, not builtupdated Jan 2023Oct 2022granted Dec 2022Jan 2023
Unit 2 To 5, Hazeley Enterprise Parkrooftop solarrooftop solar0.2approved, not builtupdated Jun 2022May 2022granted Jul 2022Jun 2022
Fusion, Parkwayrooftop solarrooftop solar0.2approved, not builtupdated Jul 2023May 2023granted Jul 2023Jul 2023
Winchester Sport And Leisure Park, Bar End Roadrooftop solarrooftop solar0.2application submittedApr 2026——
Three Maids Hill Solar Farmbattery storagebattery storage—abandonedupdated Jul 2024Oct 2020granted May 2021Jul 2024
IBM Hursleysolar farmsolar farm—approved, not builtupdated Jul 2024Mar 2024granted Jun 2024Jul 2024
Titchfield Lane, Wickhambattery storagebattery storage—approved, not builtupdated Mar 2026Jan 2025granted Mar 2026Mar 2026
Glebe Farm, Curdridge Lanebattery storagebattery storage—application submittedupdated Jul 2025May 2025—Jul 2025
Hawks Nest Farmbattery storagebattery storage—refusedupdated Jan 2025Nov 2024refused Jan 2025Jan 2025
Micheldever Tyres Winchester, Winnall Warehouserooftop solarrooftop solar—approved, not builtupdated Apr 2026Dec 2025granted Jan 2026Apr 2026

Postcode districts in Winchester

DistrictProjects within 10 kmPendingApprovedOperational
PO17436286
SO2115193
SO2215193
SO2315193
SO244201
SO32354234

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Projects belong to Winchester by location (nearest postcode to the REPD grid reference); decisions are counted by the planning authority named in REPD.