New Farm House Locks Farm (18 MW solar farm)

New Farm House Locks Farm is an 18 MW solar farm project in Winchester, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 9 June 2023, not yet built; the record was last updated on 11 October 2024. REPD records the planning permission as expiring on 9 June 2026, but the project holds a Contracts for Difference award (AR6), so construction may have started. Check the planning authority's register for the latest position.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

18 MWsolar farm
approved, not builtmay be out of datestatus in REPD
11 October 2024record last updated
Winchestercouncil area

REPD records the planning permission as expiring on 9 June 2026, but the project holds a Contracts for Difference award (AR6), so construction may have started.

Planning timeline

DateStage
8 June 2021Application submitted
9 June 2023Planning permission granted
9 June 2026Permission expired

Project details

Technology
solar farm
Capacity
18 MW
Status (REPD)
approved, not built
Record last updated
11 October 2024
Operator or applicant
Nextpower Spv 12 Limited
Planning authority
Winchester
Planning application reference
21/01391/FUL
Site area
34.0 ha
Address (REPD)
New Farm House, Locks Farm, Botley Road, Bishops Waltham, Southampton, Hampshire
Council area (by location)
Winchester
Time to decision
104 weeks
Contracts for Difference
AR6
REPD reference
7924

Who decides

ApplicationsWinchesterUK
Decided applications (solar, wind, battery)3710,236
Refused4 (11%)19%
Solar refused0 of 2412%
Onshore wind refused3 of 345%
Battery storage refused1 of 1016%
Median time from submission to decision14.7 weeks17.0 weeks
Appeals lodged / allowed3 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Bishop’s Waltham Solar Farmsolar farm12operational0.8
Glebe Farm, Curdridge Lane Solar Farmsolar farm10application submitted0.8
Raglington Farmsolar farm5.8operational2.8
Titchfield Lane, Wickhamsolar farm49.9approved, not built4.5
Fontley House Farmsolar farm10approved, not built5.2
Ash Farm, Titchfield Lanebattery storage15approved, not built6.2
Chalcroft Solar Parksolar farm6.3operational6.3
Allington Lane Solar & Battery Farmsolar farm27approved, not built6.5
Titchfield Lanebattery storage49under construction6.5

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (50.9416, -1.2187).