Bishop’s Waltham Solar Farm (12 MW)

Bishop’s Waltham Solar Farm is a 12 MW solar farm project in Winchester, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 17 February 2017; the record was last updated on 31 May 2017.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

12 MWsolar farm
operationalstatus in REPD
31 May 2017record last updated
Winchestercouncil area

Planning timeline

DateStage
17 April 2015Application submitted
7 August 2015Planning permission granted
31 October 2016Construction started
17 February 2017Operational

Project details

Technology
solar farm
Capacity
12 MW
Status (REPD)
operational
Record last updated
31 May 2017
Operator or applicant
Solafields U/Bishop's Waltham Renewables Ltd
Planning authority
Winchester
Planning application reference
15/00786/FUL
Site area
28.4 ha
Address (REPD)
Winchester Road, Bishops Waltham
Council area (by location)
Winchester
Time to decision
16 weeks
REPD reference
1325

Who decides

ApplicationsWinchesterUK
Decided applications (solar, wind, battery)3710,236
Refused4 (11%)19%
Solar refused0 of 2412%
Onshore wind refused3 of 345%
Battery storage refused1 of 1016%
Median time from submission to decision14.7 weeks17.0 weeks
Appeals lodged / allowed3 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
New Farm House Locks Farmsolar farm18approved, not built0.8
Glebe Farm, Curdridge Lane Solar Farmsolar farm10application submitted1.0
Raglington Farmsolar farm5.8operational3.4
Titchfield Lane, Wickhamsolar farm49.9approved, not built4.7
Fontley House Farmsolar farm10approved, not built5.4
Ash Farm, Titchfield Lanebattery storage15approved, not built6.5
Titchfield Lanebattery storage49under construction6.8
Funtley Solar Photovoltaic PV Farmsolar farm10.5application submitted7.0
Chalcroft Solar Parksolar farm6.3operational7.0

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (50.9443, -1.2081).