Energy Projects Near You

Titchfield Lane, Wickham (49.9 MW solar farm)

Titchfield Lane, Wickham is a 49.9 MW solar farm project in Winchester, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 25 September 2025, not yet built; the record was last updated on 7 November 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

49.9 MWsolar farm
approved, not builtstatus in REPD
7 November 2025record last updated
Winchestercouncil area

Planning timeline

DateStage
3 February 2025Application submitted
25 September 2025Planning permission granted
25 September 2028Permission due to expire (unless work starts)

Project details

Technology
solar farm
Capacity
49.9 MW
Status (REPD)
approved, not built
Record last updated
7 November 2025
Operator or applicant
Conrad Energy (Developments) II Limited
Planning authority
Winchester
Planning application reference
24/02804/FUL
Site area
63.0 ha
Address (REPD)
Titchfield Lane Wickham
Council area (by location)
Winchester
Time to decision
33 weeks
Name in REPD
Titchfield Lane, Wickham - Solar Panels
REPD reference
18186

Who decides

ApplicationsWinchesterUK
Decided applications (solar, wind, battery)3710,236
Refused4 (11%)19%
Solar refused0 of 2412%
Onshore wind refused3 of 345%
Battery storage refused1 of 1016%
Median time from submission to decision14.7 weeks17.0 weeks
Appeals lodged / allowed3 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Fontley House Farmsolar farm10approved, not built0.9
Ash Farm, Titchfield Lanebattery storage15approved, not built2.1
Titchfield Lanebattery storage49under construction2.3
Funtley Solar Photovoltaic PV Farmsolar farm10.5application submitted2.6
Raglington Farmsolar farm5.8operational2.7
Funtley Refuse Tipsolar farm10permission expired2.8
Glebe Farm, Curdridge Lane Solar Farmsolar farm10application submitted3.7
New Farm House Locks Farmsolar farm18approved, not built4.5
Bishop’s Waltham Solar Farmsolar farm12operational4.7

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (50.9025, -1.2029).