Raglington Farm (5.8 MW solar farm)
Raglington Farm is a 5.8 MW solar farm project in Winchester, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 31 August 2013; the record was last updated on 26 July 2018.
5.8 MWsolar farm
operationalstatus in REPD
26 July 2018record last updated
Winchestercouncil area
Planning timeline
| Date | Stage |
|---|---|
| 10 April 2012 | Application submitted |
| 10 July 2012 | Planning permission granted |
| 31 August 2013 | Operational |
Project details
- Technology
- solar farm
- Capacity
- 5.8 MW
- Status (REPD)
- operational
- Record last updated
- 26 July 2018
- Operator or applicant
- NextEnery Solar Fund (NESF)
- Planning authority
- Winchester
- Planning application reference
- 12/00913/FUL
- Address (REPD)
- Raglington Farm, Botley Road, Shedfield, Southampton
- Council area (by location)
- Winchester
- Time to decision
- 13 weeks
- REPD reference
- 1418
Who decides
| Applications | Winchester | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 37 | 10,236 |
| Refused | 4 (11%) | 19% |
| Solar refused | 0 of 24 | 12% |
| Onshore wind refused | 3 of 3 | 45% |
| Battery storage refused | 1 of 10 | 16% |
| Median time from submission to decision | 14.7 weeks | 17.0 weeks |
| Appeals lodged / allowed | 3 / 0 | — |
Other large projects within 10 km
| Project | Type | MW | Status | km |
|---|---|---|---|---|
| Glebe Farm, Curdridge Lane Solar Farm | solar farm | 10 | application submitted | 2.4 |
| Titchfield Lane, Wickham | solar farm | 49.9 | approved, not built | 2.7 |
| New Farm House Locks Farm | solar farm | 18 | approved, not built | 2.8 |
| Fontley House Farm | solar farm | 10 | approved, not built | 3.0 |
| Bishop’s Waltham Solar Farm | solar farm | 12 | operational | 3.4 |
| Ash Farm, Titchfield Lane | battery storage | 15 | approved, not built | 3.7 |
| Titchfield Lane | battery storage | 49 | under construction | 4.0 |
| Funtley Solar Photovoltaic PV Farm | solar farm | 10.5 | application submitted | 4.1 |
| Funtley Refuse Tip | solar farm | 10 | permission expired | 4.3 |
Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (50.9179, -1.2323).