Titchfield Lane (49 MW battery storage)

Titchfield Lane is a 49 MW battery storage project in Winchester, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: under construction since 20 August 2023; the record was last updated on 20 August 2023.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

49 MWbattery storage
under constructionstatus in REPD
20 August 2023record last updated
Winchestercouncil area

Planning timeline

DateStage
4 December 2019Application submitted
20 August 2020Planning permission granted
20 August 2023Construction started

Project details

Technology
battery storage (stand-alone storage)
Capacity
49 MW
Status (REPD)
under construction
Record last updated
20 August 2023
Operator or applicant
Balanced Grid Solutions
Planning authority
Winchester
Planning application reference
19/02710/FUL
Address (REPD)
Land South Of Ash Farm, Titchfield Lane, Wickham, Fareham, Hampshire
Council area (by location)
Winchester
Time to decision
37 weeks
REPD reference
7828

Who decides

ApplicationsWinchesterUK
Decided applications (solar, wind, battery)3710,236
Refused4 (11%)19%
Solar refused0 of 2412%
Onshore wind refused3 of 345%
Battery storage refused1 of 1016%
Median time from submission to decision14.7 weeks17.0 weeks
Appeals lodged / allowed3 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Funtley Solar Photovoltaic PV Farmsolar farm10.5application submitted0.3
Ash Farm, Titchfield Lanebattery storage15approved, not built0.4
Funtley Refuse Tipsolar farm10permission expired0.5
Fontley House Farmsolar farm10approved, not built1.4
Titchfield Lane, Wickhamsolar farm49.9approved, not built2.3
Raglington Farmsolar farm5.8operational4.0
Glebe Farm, Curdridge Lane Solar Farmsolar farm10application submitted5.8
Newlands Farm Battery Storage Facility Phase 2battery storage40operational5.8
Newlands Farm Solarsolar farm20.5operational5.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (50.8833, -1.2155).