Funtley Refuse Tip (10 MW solar farm)

Funtley Refuse Tip is a 10 MW solar farm project in Winchester, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: planning permission expired on 28 August 2016; the record was last updated on 18 September 2017.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

10 MWsolar farm
permission expiredstatus in REPD
18 September 2017record last updated
Winchestercouncil area

Planning timeline

DateStage
5 June 2013Application submitted
28 August 2013Planning permission granted
28 August 2016Permission expired

Project details

Technology
solar farm
Capacity
10 MW
Status (REPD)
permission expired
Record last updated
18 September 2017
Operator or applicant
Cassidy & Ashton Group Ltd
Planning authority
Winchester
Planning application reference
13/01247/FUL
Site area
23.0 ha
Address (REPD)
Funtley Refuse Tip, Titchfield Lane, Wickham, Fareham, Hampshire, PO15 6DY
Council area (by location)
Winchester
Time to decision
12 weeks
REPD reference
1821

Who decides

ApplicationsWinchesterUK
Decided applications (solar, wind, battery)3710,236
Refused4 (11%)19%
Solar refused0 of 2412%
Onshore wind refused3 of 345%
Battery storage refused1 of 1016%
Median time from submission to decision14.7 weeks17.0 weeks
Appeals lodged / allowed3 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Funtley Solar Photovoltaic PV Farmsolar farm10.5application submitted0.2
Titchfield Lanebattery storage49under construction0.5
Ash Farm, Titchfield Lanebattery storage15approved, not built0.7
Fontley House Farmsolar farm10approved, not built1.9
Titchfield Lane, Wickhamsolar farm49.9approved, not built2.8
Raglington Farmsolar farm5.8operational4.3
Newlands Farm Battery Storage Facility Phase 2battery storage40operational5.6
Newlands Farm Solarsolar farm20.5operational5.7
Tanners Lane Battery Energy Storage Facility (Phase One)battery storage40approved, not built5.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (50.8802, -1.2206).