Tanners Lane Battery Energy Storage Facility (Phase One) (40 MW)
Tanners Lane Battery Energy Storage Facility (Phase One) is a 40 MW battery storage project in Fareham, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 26 November 2019, not yet built; the record was last updated on 7 April 2022. REPD also records that the planning permission expired on 26 November 2022, so the project may not go ahead in this form. Check the planning authority's register for the latest position.
REPD also records that the planning permission expired on 26 November 2022, so the project may not go ahead in this form.
Planning timeline
| Date | Stage |
|---|---|
| 2 September 2019 | Application submitted |
| 26 November 2019 | Planning permission granted |
| 26 November 2022 | Permission expired |
Project details
- Technology
- battery storage (stand-alone storage)
- Capacity
- 40 MW
- Status (REPD)
- approved, not built
- Record last updated
- 7 April 2022
- Operator or applicant
- British Solar Renewables
- Planning authority
- Fareham
- Planning application reference
- P/19/1019/FP
- Address (REPD)
- Newlands Farm Tanners Lane Fareham
- Council area (by location)
- Fareham
- Time to decision
- 12 weeks
- Name in REPD
- Tanners Lane - Battery Energy Storage Facility (Phase One)
- REPD reference
- 9708
Who decides
Fareham has 9 decided solar, wind or battery applications in REPD — too few for a refusal rate (we show one from 10 decisions). Across all UK planning authorities 19% of 10,236 decisions were refusals.
Other large projects within 10 km
| Project | Type | MW | Status | km |
|---|---|---|---|---|
| Newlands Farm Battery Storage Facility Phase 2 | battery storage | 40 | operational | 0.2 |
| Newlands Farm Solar | solar farm | 20.5 | operational | 0.5 |
| Peel Common Waste Water Treatment Works | battery storage | 20 | abandoned | 1.4 |
| Funtley Refuse Tip | solar farm | 10 | permission expired | 5.8 |
| Funtley Solar Photovoltaic PV Farm | solar farm | 10.5 | application submitted | 5.9 |
| Titchfield Lane | battery storage | 49 | under construction | 6.0 |
| Ash Farm, Titchfield Lane | battery storage | 15 | approved, not built | 6.3 |
| Fontley House Farm | solar farm | 10 | approved, not built | 7.2 |
| Titchfield Lane, Wickham | solar farm | 49.9 | approved, not built | 7.9 |
Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (50.8321, -1.1896).