Energy Projects Near You

Solar, wind and battery projects near Southampton (SO32)

35 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of SO32 (Winchester): 4 are waiting for a planning decision, 23 approved but not yet running, 4 operational. The largest live scheme is Titchfield Lane, Wickham (49.9 MW solar farm, approved on 25 September 2025, not yet built), 5.1 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

35projects within 10 km
4awaiting a decision
23approved, not running
4operational

Projects within 10 km of SO32

Projects of 1 MW and more (18)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Bishop’s Waltham Solar Farmsolar farmsolar farm12operationalupdated May 2017Apr 2015granted Aug 2015May 2017Winchester0.4
Forest Farmsolar farmsolar farm3operationalupdated May 2017Feb 2015granted Dec 2015May 2017Winchester0.7
New Farm House Locks Farmsolar farmsolar farm18approved, not built may be out of dateupdated Oct 2024Jun 2021granted Jun 2023Oct 2024Winchester0.9
Glebe Farm, Curdridge Lane Solar Farmsolar farmsolar farm10application submittedupdated Jul 2025May 2025—Jul 2025Winchester1.4
Raglington Farmsolar farmsolar farm5.8operationalupdated Jul 2018Apr 2012granted Jul 2012Jul 2018Winchester3.7
Titchfield Lane, Wickhamsolar farmsolar farm49.9approved, not builtupdated Nov 2025Feb 2025granted Sep 2025Nov 2025Winchester5.1
Fontley House Farmsolar farmsolar farm10approved, not built may be out of dateupdated Aug 2020Apr 2016granted May 2017Aug 2020Winchester5.8
Allington Lane Solar & Battery Farmsolar farmsolar farm27approved, not builtupdated Jul 2025Dec 2023granted Jul 2024Jul 2025Eastleigh6.8
Allington Lane Solar & Battery Farmbattery storagebattery storage16approved, not builtupdated Jul 2025Dec 2023granted Jul 2024Jul 2025Eastleigh6.8
Ash Farm, Titchfield Lanebattery storagebattery storage15approved, not builtupdated Mar 2025May 2023granted Feb 2025Mar 2025Winchester6.9
Chalcroft Solar Parksolar farmsolar farm6.3operationalupdated Apr 2013Sep 2012granted Dec 2012Apr 2013Eastleigh6.9
Titchfield Lanebattery storagebattery storage49under constructionupdated Aug 2023Dec 2019granted Aug 2020Aug 2023Winchester7.2
Funtley Solar Photovoltaic PV Farmsolar farmsolar farm10.5application submittedupdated Oct 2024Sep 2024—Oct 2024Winchester7.4
Funtley Refuse Tipsolar farmsolar farm10permission expiredupdated Sep 2017Jun 2013granted Aug 2013Sep 2017Winchester7.5
ATS, Sopwith Way - Ground Mounted Solar Photovoltaic Arrayssolar farmsolar farm3.3approved, not builtupdated Jul 2024Sep 2023granted Jun 2024Jul 2024Fareham8.7
Concorde Way, Segensworthrooftop solarrooftop solar1under constructionupdated Jul 2022Jul 2022granted Nov 2022Jul 2022Fareham8.9
Solarsolarsolar1abandonedupdated Jul 2019Oct 2013granted Mar 2014Jul 2019Eastleigh9.4
Lower Russells Fieldsolarsolar1permission expiredupdated Sep 2017Dec 2013granted May 2014Sep 2017Eastleigh9.7
Smaller schemes under 1 MW, mostly rooftop solar (17)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Glebe Farm, Curdridge Lanebattery storagebattery storage—application submittedupdated Jul 2025May 2025—Jul 2025Winchester1.4
Hawks Nest Farmbattery storagebattery storage—refusedupdated Jan 2025Nov 2024refused Jan 2025Jan 2025Winchester3.6
Titchfield Lane, Wickhambattery storagebattery storage—approved, not builtupdated Mar 2026Jan 2025granted Mar 2026Mar 2026Winchester6.9
Hoads Hill Reservoirsolar farmsolar farm0.2approved, not builtupdated Sep 2021Jul 2021granted Sep 2021Sep 2021Fareham7.0
Sainsbury Supermarket, Tollbar Wayrooftop solarrooftop solar0.8approved, not builtupdated Apr 2025Jan 2025granted Mar 2025Apr 2025Eastleigh7.7
Fusion, Parkwayrooftop solarrooftop solar0.2approved, not builtupdated Jul 2023May 2023granted Jul 2023Jul 2023Winchester8.1
Fusion, Parkwayrooftop solarrooftop solar0.2approved, not builtupdated Jul 2023May 2023granted Jul 2023Jul 2023Winchester8.3
Holiday Inn Express, Botley Roadrooftop solarrooftop solar0.2approved, not builtupdated Jun 2025Apr 2025granted May 2025Jun 2025Eastleigh8.4
Utilita Bowl, Marshall Driverooftop solarrooftop solar0.4approved, not builtupdated Jun 2024Mar 2024granted May 2024Jun 2024Eastleigh8.4
National Air Traffic Services, Sopwith Wayrooftop solarrooftop solar1approved, not builtupdated Sep 2023Jul 2023granted Aug 2023Sep 2023Fareham8.6
Strategic Park, Comines Wayrooftop solarrooftop solar0.4application submitted may be out of dateupdated Oct 2022Oct 2022—Oct 2022Eastleigh8.6
Unit 1, Strategic Park, Comines Wayrooftop solarrooftop solar0.3approved, not builtupdated Sep 2022Aug 2022granted Sep 2022Sep 2022Eastleigh8.6
CooperVision, Concorde Way - Unit 8 - Solar Panelsrooftop solarrooftop solar0.9approved, not builtupdated Jun 2025Apr 2025granted Jun 2025Jun 2025Winchester9.0
Octagon House, Concorde Wayrooftop solarrooftop solar0.4approved, not builtupdated Dec 2023Nov 2023granted Dec 2023Dec 2023Winchester9.0
Pet Centre Garsons Garden Centre, Fontley Roadrooftop solarrooftop solar0.2approved, not builtupdated Jan 2023Oct 2022granted Dec 2022Jan 2023Winchester9.1
Allington Lane, West Endrooftop solarrooftop solar0.5approved, not builtupdated Nov 2021Oct 2021granted Nov 2021Nov 2021Eastleigh9.4
Itchen Power, West Endsolar farmsolar farm0.2approved, not built may be out of dateupdated Oct 2021Oct 2021granted Jan 2022Oct 2021Eastleigh9.8

Distance from the average position of the SO32 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm142740129
Rooftop solar13112006.7
Solar200000
Battery storage6140180

MW in pipeline: pending, approved and under-construction capacity.

How Winchester decides solar, wind and battery applications

ApplicationsWinchesterUK
Decided applications (solar, wind, battery)3710,236
Refused4 (11%)19%
Solar refused0 of 2412%
Onshore wind refused3 of 345%
Battery storage refused1 of 1016%
Median time from submission to decision14.7 weeks17.0 weeks
Appeals lodged / allowed3 / 0—

All projects in Winchester

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near SO32, 4 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.