Allington Lane Solar & Battery Farm (27 MW)

Allington Lane Solar & Battery Farm is a 27 MW solar farm project in Eastleigh, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 26 July 2024, not yet built; the record was last updated on 15 July 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

27 MWsolar farm
approved, not builtstatus in REPD
15 July 2025record last updated
Eastleighcouncil area

Planning timeline

DateStage
21 December 2023Application submitted
26 July 2024Planning permission granted
26 July 2027Permission due to expire (unless work starts)

Project details

Technology
solar farm
Capacity
27 MW
Status (REPD)
approved, not built
Record last updated
15 July 2025
Operator or applicant
Eastleigh Borough Council
Planning authority
Eastleigh
Planning application reference
F/23/96527
Site area
37.7 ha
Address (REPD)
We/O Allington Lane, Eastleigh
Council area (by location)
Eastleigh
Time to decision
31 weeks
Name in REPD
Allington Lane - Solar & Battery Farm
REPD reference
14584

The scheme also includes 16 MW of battery storage, recorded separately in REPD (approved, not built).

Who decides

ApplicationsEastleighUK
Decided applications (solar, wind, battery)1910,236
Refused0 (0%)19%
Solar refused0 of 1712%
Battery storage refused0 of 216%
Median time from submission to decision10.3 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Chalcroft Solar Parksolar farm6.3operational1.5
New Farm House Locks Farmsolar farm18approved, not built6.5
Bishop’s Waltham Solar Farmsolar farm12operational7.1
Raglington Farmsolar farm5.8operational7.1
Glebe Farm, Curdridge Lane Solar Farmsolar farm10application submitted7.2
Silkstead Farm, Poles Lanebattery storage49.9approved, not built7.5
Butts Field, Mill Lanebattery storage99approved, not built7.9
Field House Solar / Hursley Roadsolar farm6.4operational7.9
Netley Landfill Solarsolar farm12operational8.3

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (50.963, -1.3045).