Butts Field, Mill Lane (99 MW battery storage)

Butts Field, Mill Lane is a 99 MW battery storage project in Southampton, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 3 October 2024, not yet built; the record was last updated on 7 May 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

99 MWbattery storage
approved, not builtstatus in REPD
7 May 2025record last updated
Southamptoncouncil area

Planning timeline

DateStage
23 November 2023Application submitted
3 October 2024Planning permission granted
3 October 2027Permission due to expire (unless work starts)

Project details

Technology
battery storage (stand-alone storage)
Capacity
99 MW
Status (REPD)
approved, not built
Record last updated
7 May 2025
Operator or applicant
Ecotricity Generation Limited
Planning authority
Southampton
Planning application reference
23/02942/FULLS
Address (REPD)
Butts Field Mill Lane, Nursling, Southampton
Council area (by location)
Southampton
Time to decision
45 weeks
Name in REPD
Butts Field, Mill Lane - Battery Storage
REPD reference
13573

Who decides

ApplicationsSouthamptonUK
Decided applications (solar, wind, battery)1610,236
Refused2 (12%)19%
Solar refused1 of 1412%
Battery storage refused1 of 216%
Median time from submission to decision7.8 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Netley Landfill Solarsolar farm12operational1.0
Weston Lanebattery storage49.9refused1.0
Hamble Lane Battery Energy Storagebattery storage6approved, not built2.3
Chalcroft Solar Parksolar farm6.3operational6.4
East Road, Marchwoodbattery storage200approved, not built6.7
Allington Lane Solar & Battery Farmsolar farm27approved, not built7.9
Tavells Lane Solar Farmsolar farm5.3operational8.1
Raglington Farmsolar farm5.8operational8.1
Funtley Refuse Tipsolar farm10permission expired8.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (50.8963, -1.3432).