Solar, wind and battery projects near Southampton (SO14)
61 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of SO14 (Southampton): 3 are waiting for a planning decision, 41 approved but not yet running, 6 operational. The largest live scheme is East Road, Marchwood (200 MW battery storage, approved on 13 November 2025, not yet built), 3.1 km away. Source: Renewable Energy Planning Database, July 2026 extract.
Projects within 10 km of SO14
Projects of 1 MW and more (29)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| East Road, Marchwoodbattery storage | battery storage | 200 | approved, not builtupdated Dec 2025 | Jul 2025 | granted Nov 2025 | Dec 2025 | New Forest | 3.1 |
| Weston Lanebattery storage | battery storage | 49.9 | refusedupdated Jul 2025 | Nov 2023 | refused Jun 2025 | Jul 2025 | Southampton | 3.3 |
| Butts Field, Mill Lanebattery storage | battery storage | 99 | approved, not builtupdated May 2025 | Nov 2023 | granted Oct 2024 | May 2025 | Southampton | 4.0 |
| Tavells Lane Solar Farmsolar farm | solar farm | 5.3 | operationalupdated Apr 2013 | Mar 2012 | granted May 2012 | Apr 2013 | New Forest | 4.5 |
| Land South of Bury Roadsolar farm | solar farm | 4 | abandonedupdated Apr 2018 | Aug 2015 | granted Sep 2015 | Apr 2018 | New Forest | 4.8 |
| Netley Landfill Solarsolar farm | solar farm | 12 | operationalupdated Sep 2018 | Aug 2014 | granted Oct 2014 | Sep 2018 | Eastleigh | 4.9 |
| Lower Russells Fieldsolar | solar | 1 | permission expiredupdated Sep 2017 | Dec 2013 | granted May 2014 | Sep 2017 | Eastleigh | 5.1 |
| Bulls Copse Road, Marchwood Bypassbattery storage | battery storage | 49.9 | approved, not builtupdated Mar 2026 | Jul 2025 | granted Feb 2026 | Mar 2026 | New Forest | 5.4 |
| Hamble Lane Battery Energy Storagebattery storage | battery storage | 6 | approved, not built may be out of dateupdated Jan 2020 | Apr 2019 | granted Nov 2019 | Jan 2020 | Eastleigh | 5.9 |
| Durley Farmsolar farm | solar farm | 6.7 | application withdrawnupdated Jul 2014 | May 2014 | — | Jul 2014 | New Forest | 6.7 |
| Tesco Distribution, Canberra Roadrooftop solar | rooftop solar | 2.1 | application withdrawnupdated Nov 2024 | Oct 2024 | — | Nov 2024 | Test Valley | 6.9 |
| Upton Lane, Nurslingbattery storage | battery storage | 99.9 | approved, not builtupdated Jun 2025 | Oct 2024 | granted May 2025 | Jun 2025 | Test Valley | 7.0 |
| Upton Lane, Nurslingbattery storage | battery storage | 50 | approved, not built may be out of dateupdated Aug 2025 | Sep 2021 | granted Jan 2022 | Aug 2025 | Test Valley | 7.0 |
| Station Roadbattery storage | battery storage | 49.5 | application withdrawnupdated Nov 2018 | May 2017 | — | Nov 2018 | Test Valley | 7.1 |
| Solarsolar | solar | 1 | abandonedupdated Jul 2019 | Oct 2013 | granted Mar 2014 | Jul 2019 | Eastleigh | 7.2 |
| Station Road, Crescent Industrial Estatebattery storage | battery storage | 62 | approved, not builtupdated Mar 2026 | May 2025 | granted Jan 2026 | Mar 2026 | Test Valley | 7.3 |
| CooperVision, Ensign Wayrooftop solar | rooftop solar | 1.4 | approved, not builtupdated Oct 2024 | Aug 2024 | granted Sep 2024 | Oct 2024 | Eastleigh | 7.4 |
| Testwood Water Supply Workssolar farm | solar farm | 1.9 | operationalupdated Sep 2017 | Jul 2016 | granted Dec 2016 | Sep 2017 | New Forest | 7.6 |
| Mill Lane, Nurslingbattery storage | battery storage | 20 | under constructionupdated Mar 2022 | Nov 2019 | granted May 2020 | Mar 2022 | Test Valley | 7.7 |
| Chalcroft Solar Parksolar farm | solar farm | 6.3 | operationalupdated Apr 2013 | Sep 2012 | granted Dec 2012 | Apr 2013 | Eastleigh | 7.8 |
| Misslebrook Farm, Botley Roadbattery storage | battery storage | 60 | approved, not builtupdated Oct 2025 | Jan 2023 | granted Apr 2024 | Oct 2025 | Test Valley | 8.1 |
| ATS, Sopwith Way - Ground Mounted Solar Photovoltaic Arrayssolar farm | solar farm | 3.3 | approved, not builtupdated Jul 2024 | Sep 2023 | granted Jun 2024 | Jul 2024 | Fareham | 8.4 |
| Grove Solar Park (Phase 2)solar farm | solar farm | 11 | operationalupdated Jan 2017 | Jul 2014 | granted Sep 2015 | Jan 2017 | Test Valley | 8.5 |
| Grove Solar Park (Phase 1)solar farm | solar farm | 5 | operationalupdated Jul 2016 | Jul 2014 | granted Sep 2015 | Jul 2016 | Test Valley | 8.5 |
| Fletchwood Lane, Totton Solar Parksolar farm | solar farm | 5.3 | refusedupdated May 2026 | Jul 2025 | refused Mar 2026 | May 2026 | New Forest | 8.7 |
| Thornlands Farm, Fletchwood Road Solar Farmsolar farm | solar farm | 12 | refusedupdated Jul 2024 | Feb 2024 | refused Jun 2024 | Jul 2024 | New Forest | 8.7 |
| Allington Lane Solar & Battery Farmsolar farm | solar farm | 27 | approved, not builtupdated Jul 2025 | Dec 2023 | granted Jul 2024 | Jul 2025 | Eastleigh | 9.0 |
| Allington Lane Solar & Battery Farmbattery storage | battery storage | 16 | approved, not builtupdated Jul 2025 | Dec 2023 | granted Jul 2024 | Jul 2025 | Eastleigh | 9.0 |
| Land South Of Carlton Housesolar farm | solar farm | 2.2 | refusedupdated Jan 2016 | Oct 2015 | refused Dec 2015 | Jan 2016 | New Forest | 10.0 |
Smaller schemes under 1 MW, mostly rooftop solar (32)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Saxon House, Lower York Streetrooftop solar | rooftop solar | — | approved, not builtupdated May 2021 | Mar 2021 | granted May 2021 | May 2021 | Southampton | 0.7 |
| Harbour Parade Solar Photovoltaicsrooftop solar | rooftop solar | — | approved, not builtupdated Aug 2025 | Jun 2025 | granted Jul 2025 | Aug 2025 | Southampton | 1.0 |
| West Quay Retail Park, Harbour Paraderooftop solar | rooftop solar | — | approved, not builtupdated Jan 2026 | Oct 2025 | granted Dec 2025 | Jan 2026 | Southampton | 1.0 |
| Lucia Foster Welch Student Hall Of Residencerooftop solar | rooftop solar | — | approved, not built may be out of dateupdated Oct 2022 | Jul 2022 | granted Sep 2022 | Oct 2022 | Southampton | 1.0 |
| Shamrock Quay Solar Photovoltaic Equipmentrooftop solar | rooftop solar | — | refusedupdated May 2021 | Mar 2021 | refused Apr 2021 | May 2021 | Southampton | 1.3 |
| Buildings J K And Z Tesla Centre, Herbert Walker Avenuerooftop solar | rooftop solar | 0.8 | approved, not builtupdated Jan 2023 | Nov 2022 | granted Jan 2023 | Jan 2023 | Southampton | 1.8 |
| Grosvenor House & Belmont House, Portswood Roadrooftop solar | rooftop solar | 0.2 | approved, not builtupdated May 2025 | Feb 2025 | granted Apr 2025 | May 2025 | Southampton | 2.3 |
| Spire Hospital, Chalybeate Closerooftop solar | rooftop solar | 0.2 | approved, not builtupdated May 2024 | Mar 2024 | granted May 2024 | May 2024 | Southampton | 3.6 |
| Southampton General Hospital, Tremona Roadrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Feb 2024 | Dec 2023 | granted Feb 2024 | Feb 2024 | Southampton | 3.9 |
| Antelope Retail Park, Bursledon Roadrooftop solar | rooftop solar | 0.7 | approved, not builtupdated Jun 2026 | Feb 2026 | granted Apr 2026 | Jun 2026 | Southampton | 4.0 |
| Slowhill Copse, Bury Roadbattery storage | battery storage | — | approved, not builtupdated May 2025 | Dec 2024 | granted Apr 2025 | May 2025 | New Forest | 4.7 |
| Staplewood Campus, Marchwoodrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Sep 2025 | Jul 2025 | granted Aug 2025 | Sep 2025 | New Forest | 4.8 |
| Airways Distribution Park, Wide Lane, Unit 1rooftop solar | rooftop solar | 0.5 | approved, not builtupdated Feb 2025 | Dec 2024 | granted Jan 2025 | Feb 2025 | Southampton | 4.9 |
| Airways Distribution Park, Wide Lanerooftop solar | rooftop solar | 0.3 | approved, not builtupdated Jun 2023 | Apr 2023 | granted Jun 2023 | Jun 2023 | Southampton | 4.9 |
| Itchen Power, West Endsolar farm | solar farm | 0.2 | approved, not built may be out of dateupdated Oct 2021 | Oct 2021 | granted Jan 2022 | Oct 2021 | Eastleigh | 4.9 |
| Pei Genesis UK Limited, George Curl Wayrooftop solar | rooftop solar | 0.3 | approved, not builtupdated Feb 2023 | Dec 2022 | granted Jan 2023 | Feb 2023 | Eastleigh | 5.1 |
| Allington Lane, West Endrooftop solar | rooftop solar | 0.5 | approved, not builtupdated Nov 2021 | Oct 2021 | granted Nov 2021 | Nov 2021 | Eastleigh | 5.2 |
| Strategic Park, Comines Wayrooftop solar | rooftop solar | 0.4 | application submitted may be out of dateupdated Oct 2022 | Oct 2022 | — | Oct 2022 | Eastleigh | 5.4 |
| Unit 1, Strategic Park, Comines Wayrooftop solar | rooftop solar | 0.3 | approved, not builtupdated Sep 2022 | Aug 2022 | granted Sep 2022 | Sep 2022 | Eastleigh | 5.4 |
| Utilita Bowl, Marshall Driverooftop solar | rooftop solar | 0.4 | approved, not builtupdated Jun 2024 | Mar 2024 | granted May 2024 | Jun 2024 | Eastleigh | 5.5 |
| Holiday Inn Express, Botley Roadrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Jun 2025 | Apr 2025 | granted May 2025 | Jun 2025 | Eastleigh | 5.5 |
| Asquith Nursery, David Lloyd Leisurerooftop solar | rooftop solar | 0.3 | approved, not builtupdated Feb 2024 | Dec 2023 | granted Jan 2024 | Feb 2024 | Test Valley | 5.7 |
| Hound Roadbattery storage | battery storage | — | application submitted may be out of dateupdated Sep 2021 | Sep 2020 | — | Sep 2021 | Eastleigh | 5.7 |
| Test Valley Business Centre, Test Lanerooftop solar | rooftop solar | 0.3 | approved, not builtupdated Nov 2022 | Oct 2022 | granted Nov 2022 | Nov 2022 | Southampton | 5.9 |
| Sainsbury Supermarket, Tollbar Wayrooftop solar | rooftop solar | 0.8 | approved, not builtupdated Apr 2025 | Jan 2025 | granted Mar 2025 | Apr 2025 | Eastleigh | 6.2 |
| Chandlers Fordrooftop solar | rooftop solar | 0.2 | approved, not builtupdated May 2022 | May 2022 | granted Jun 2022 | May 2022 | Eastleigh | 6.5 |
| Mauretania Road, Nurslingrooftop solar | rooftop solar | 0.2 | application submitted may be out of dateupdated Jul 2023 | Jul 2023 | — | Jul 2023 | Test Valley | 6.9 |
| South Point, Hamble-Le-Ricerooftop solar | rooftop solar | 0.5 | approved, not builtupdated Nov 2024 | Aug 2024 | granted Sep 2024 | Nov 2024 | Eastleigh | 7.4 |
| Cooper Vision, Speedwell Closerooftop solar | rooftop solar | 0.6 | approved, not builtupdated Nov 2024 | Aug 2024 | granted Oct 2024 | Nov 2024 | Eastleigh | 7.8 |
| National Air Traffic Services, Sopwith Wayrooftop solar | rooftop solar | 1 | approved, not builtupdated Sep 2023 | Jul 2023 | granted Aug 2023 | Sep 2023 | Fareham | 8.1 |
| Unit 2b, School Lanerooftop solar | rooftop solar | 0.3 | approved, not builtupdated Jun 2023 | May 2023 | granted Jun 2023 | Jun 2023 | Eastleigh | 8.3 |
| Morrisons Supermarket, Tottonrooftop solar | rooftop solar | 0.3 | approved, not builtupdated Oct 2022 | Sep 2022 | granted Oct 2022 | Oct 2022 | New Forest | 8.9 |
Distance from the average position of the SO14 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.
By type
| Type | All | Pending | Approved | Operational | Refused | MW in pipeline |
|---|---|---|---|---|---|---|
| Solar farm | 14 | 0 | 3 | 6 | 3 | 30.5 |
| Rooftop solar | 31 | 2 | 27 | 0 | 1 | 11.3 |
| Solar | 2 | 0 | 0 | 0 | 0 | 0 |
| Battery storage | 14 | 1 | 11 | 0 | 1 | 663 |
MW in pipeline: pending, approved and under-construction capacity.
How Southampton decides solar, wind and battery applications
| Applications | Southampton | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 16 | 10,236 |
| Refused | 2 (12%) | 19% |
| Solar refused | 1 of 14 | 12% |
| Battery storage refused | 1 of 2 | 16% |
| Median time from submission to decision | 7.8 weeks | 17.0 weeks |
| Appeals lodged / allowed | 0 / 0 | — |
Is the status up to date?
32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near SO14, 7 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.