Energy Projects Near You

Upton Lane, Nursling (50 MW battery storage)

Upton Lane, Nursling is a 50 MW battery storage project in Test Valley, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 28 January 2022, not yet built; the record was last updated on 26 August 2025. REPD also records that the planning permission expired on 28 January 2025, so the project may not go ahead in this form. Check the planning authority's register for the latest position.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

50 MWbattery storage
approved, not builtmay be out of datestatus in REPD
26 August 2025record last updated
Test Valleycouncil area

REPD also records that the planning permission expired on 28 January 2025, so the project may not go ahead in this form.

Planning timeline

DateStage
27 September 2021Application submitted
28 January 2022Planning permission granted
28 January 2025Permission expired

Project details

Technology
battery storage (stand-alone storage)
Capacity
50 MW
Status (REPD)
approved, not built
Record last updated
26 August 2025
Operator or applicant
Unknown
Planning authority
Test Valley
Planning application reference
21/02799/FULLS
Address (REPD)
Upton Lane Nursling Southampton
Council area (by location)
Test Valley
Time to decision
18 weeks
Name in REPD
Upton Lane, Nursling - Battery Storage Facility
REPD reference
9673

Who decides

ApplicationsTest ValleyUK
Decided applications (solar, wind, battery)4910,236
Refused8 (16%)19%
Solar refused7 of 4112%
Onshore wind refused0 of 145%
Battery storage refused1 of 716%
Median time from submission to decision23.6 weeks17.0 weeks
Appeals lodged / allowed4 / 3—

Other large projects within 10 km

ProjectTypeMWStatuskm
Upton Lane, Nurslingbattery storage99.9approved, not built<0.1
Station Road, Crescent Industrial Estatebattery storage62approved, not built1.1
Station Roadbattery storage49.5application withdrawn1.6
Grove Solar Park (Phase 1)solar farm5operational1.7
Grove Solar Park (Phase 2)solar farm11operational1.7
Mill Lane, Nurslingbattery storage20under construction1.8
Misslebrook Farm, Botley Roadbattery storage60approved, not built4.0
Highwood Lanesolar farm5operational5.1
Thornlands Farm, Fletchwood Road Solar Farmsolar farm12refused5.4

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (50.9492, -1.4718).