Grove Solar Park (Phase 2) (11 MW)

Grove Solar Park (Phase 2) is an 11 MW solar farm project in Test Valley, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 30 March 2016; the record was last updated on 16 January 2017.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

11 MWsolar farm
operationalstatus in REPD
16 January 2017record last updated
Test Valleycouncil area

Planning timeline

DateStage
31 July 2014Application submitted
24 December 2014Refused by the planning authority
23 April 2015Appeal lodged
4 September 2015Planning permission granted
4 September 2015Appeal allowed
18 January 2016Construction started
30 March 2016Operational

Project details

Technology
solar farm
Capacity
11 MW
Status (REPD)
operational
Record last updated
16 January 2017
Operator or applicant
Solar Century
Planning authority
Test Valley
Planning application reference
14/01826/FULLS
Appeal reference
APP/C1760/W/15/3010697
Address (REPD)
Grove Solar Park, Land west of A3057 (Romsey Road), Romsey
Council area (by location)
Test Valley
Time to decision
57 weeks
REPD reference
6163

Who decides

ApplicationsTest ValleyUK
Decided applications (solar, wind, battery)4910,236
Refused8 (16%)19%
Solar refused7 of 4112%
Onshore wind refused0 of 145%
Battery storage refused1 of 716%
Median time from submission to decision23.6 weeks17.0 weeks
Appeals lodged / allowed4 / 3—

Other large projects within 10 km

ProjectTypeMWStatuskm
Grove Solar Park (Phase 1)solar farm5operational<0.1
Upton Lane, Nurslingbattery storage50approved, not built1.7
Upton Lane, Nurslingbattery storage99.9approved, not built1.7
Station Road, Crescent Industrial Estatebattery storage62approved, not built2.3
Mill Lane, Nurslingbattery storage20under construction2.7
Station Roadbattery storage49.5application withdrawn2.9
Misslebrook Farm, Botley Roadbattery storage60approved, not built3.4
Highwood Lanesolar farm5operational3.5
Churchers Common Solar Parksolar farm5abandoned4.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (50.9636, -1.479).