Misslebrook Farm, Botley Road (60 MW battery storage)

Misslebrook Farm, Botley Road is a 60 MW battery storage project in Test Valley, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 5 April 2024, not yet built; the record was last updated on 7 October 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

60 MWbattery storage
approved, not builtstatus in REPD
7 October 2025record last updated
Test Valleycouncil area

Planning timeline

DateStage
3 January 2023Application submitted
5 April 2024Planning permission granted
5 April 2027Permission due to expire (unless work starts)

Project details

Technology
battery storage (stand-alone storage)
Capacity
60 MW
Status (REPD)
approved, not built
Record last updated
7 October 2025
Operator or applicant
Boom Developments Limited
Planning authority
Test Valley
Planning application reference
22/03346/FULLS
Address (REPD)
Misslebrook Farm Botley Road North Baddesley
Council area (by location)
Test Valley
Time to decision
65 weeks
Name in REPD
Misslebrook Farm, Botley Road - Battery Storage
REPD reference
12691

Who decides

ApplicationsTest ValleyUK
Decided applications (solar, wind, battery)4910,236
Refused8 (16%)19%
Solar refused7 of 4112%
Onshore wind refused0 of 145%
Battery storage refused1 of 716%
Median time from submission to decision23.6 weeks17.0 weeks
Appeals lodged / allowed4 / 3—

Other large projects within 10 km

ProjectTypeMWStatuskm
Churchers Common Solar Parksolar farm5abandoned2.1
Grove Solar Park (Phase 2)solar farm11operational3.4
Grove Solar Park (Phase 1)solar farm5operational3.4
Upton Lane, Nurslingbattery storage50approved, not built4.0
Upton Lane, Nurslingbattery storage99.9approved, not built4.0
Field House Solar / Hursley Roadsolar farm6.4operational4.7
Station Road, Crescent Industrial Estatebattery storage62approved, not built5.0
Highwood Lanesolar farm5operational5.2
Station Roadbattery storage49.5application withdrawn5.6

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (50.9763, -1.4347).