Station Road, Crescent Industrial Estate (62 MW battery storage)

Station Road, Crescent Industrial Estate is a 62 MW battery storage project in Test Valley, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 29 January 2026, not yet built; the record was last updated on 30 March 2026.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

62 MWbattery storage
approved, not builtstatus in REPD
30 March 2026record last updated
Test Valleycouncil area

Planning timeline

DateStage
27 May 2025Application submitted
29 January 2026Planning permission granted
29 January 2029Permission due to expire (unless work starts)

Project details

Technology
battery storage (stand-alone storage)
Capacity
62 MW
Status (REPD)
approved, not built
Record last updated
30 March 2026
Operator or applicant
PJS One Limited
Planning authority
Test Valley
Planning application reference
25/01182/FULLS
Address (REPD)
W/O Station Road, Crescent Industrial Estate, Nursling, Southampton
Council area (by location)
Test Valley
Time to decision
35 weeks
Name in REPD
Station Road, Crescent Industrial Estate - Battery Storage Facility
REPD reference
19012

Who decides

ApplicationsTest ValleyUK
Decided applications (solar, wind, battery)4910,236
Refused8 (16%)19%
Solar refused7 of 4112%
Onshore wind refused0 of 145%
Battery storage refused1 of 716%
Median time from submission to decision23.6 weeks17.0 weeks
Appeals lodged / allowed4 / 3—

Other large projects within 10 km

ProjectTypeMWStatuskm
Station Roadbattery storage49.5application withdrawn0.6
Mill Lane, Nurslingbattery storage20under construction0.7
Upton Lane, Nurslingbattery storage50approved, not built1.1
Upton Lane, Nurslingbattery storage99.9approved, not built1.1
Grove Solar Park (Phase 1)solar farm5operational2.3
Grove Solar Park (Phase 2)solar farm11operational2.3
Thornlands Farm, Fletchwood Road Solar Farmsolar farm12refused4.3
Fletchwood Lane, Totton Solar Parksolar farm5.3refused4.8
Bulls Copse Road, Marchwood Bypassbattery storage49.9approved, not built4.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (50.9433, -1.484).