Energy Projects Near You

Bulls Copse Road, Marchwood Bypass (49.9 MW battery storage)

Bulls Copse Road, Marchwood Bypass is a 49.9 MW battery storage project in New Forest, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 20 February 2026, not yet built; the record was last updated on 31 March 2026.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

49.9 MWbattery storage
approved, not builtstatus in REPD
31 March 2026record last updated
New Forestcouncil area

Planning timeline

DateStage
10 July 2025Application submitted
20 February 2026Planning permission granted
20 February 2034Permission due to expire (unless work starts)

Project details

Technology
battery storage (stand-alone storage)
Capacity
49.9 MW
Status (REPD)
approved, not built
Record last updated
31 March 2026
Operator or applicant
Sky UK Development Limited
Planning authority
New Forest
Planning application reference
25/10640
Address (REPD)
E/O Bulls Copse Road, Marchwood Bypass, Southampton
Council area (by location)
New Forest
Time to decision
32 weeks
Name in REPD
Bulls Copse Road, Marchwood Bypass - Battery Energy Storage System
REPD reference
19388

Who decides

ApplicationsNew ForestUK
Decided applications (solar, wind, battery)2610,236
Refused7 (27%)19%
Solar refused6 of 2212%
Battery storage refused1 of 416%
Median time from submission to decision11.0 weeks17.0 weeks
Appeals lodged / allowed2 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Durley Farmsolar farm6.7application withdrawn1.2
Tavells Lane Solar Farmsolar farm5.3operational1.3
East Road, Marchwoodbattery storage200approved, not built2.4
Fletchwood Lane, Totton Solar Parksolar farm5.3refused3.4
Thornlands Farm, Fletchwood Road Solar Farmsolar farm12refused3.6
Station Roadbattery storage49.5application withdrawn4.3
Mill Lane, Nurslingbattery storage20under construction4.7
Station Road, Crescent Industrial Estatebattery storage62approved, not built4.9
Upton Lane, Nurslingbattery storage50approved, not built5.5

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (50.9001, -1.4737).