Solar, wind and battery projects near Romsey (SO51)
31 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of SO51 (Test Valley): 1 is waiting for a planning decision, 19 approved but not yet running, 5 operational. The largest live scheme is Upton Lane, Nursling (99.9 MW battery storage, approved on 15 May 2025, not yet built), 5.7 km away. Source: Renewable Energy Planning Database, July 2026 extract.
Projects within 10 km of SO51
Projects of 1 MW and more (19)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Highwood Lanesolar farm | solar farm | 5 | operationalupdated Oct 2016 | May 2015 | granted Jul 2015 | Oct 2016 | Test Valley | 0.7 |
| Grove Solar Park (Phase 2)solar farm | solar farm | 11 | operationalupdated Jan 2017 | Jul 2014 | granted Sep 2015 | Jan 2017 | Test Valley | 4.0 |
| Grove Solar Park (Phase 1)solar farm | solar farm | 5 | operationalupdated Jul 2016 | Jul 2014 | granted Sep 2015 | Jul 2016 | Test Valley | 4.0 |
| Woodington Solar Farmsolar farm | solar farm | 46 | under constructionupdated Jan 2022 | Nov 2015 | granted Jul 2017 | Jan 2022 | Test Valley | 4.6 |
| Churchers Common Solar Parksolar farm | solar farm | 5 | abandonedupdated Oct 2018 | Jun 2015 | granted Dec 2015 | Oct 2018 | Test Valley | 5.2 |
| Misslebrook Farm, Botley Roadbattery storage | battery storage | 60 | approved, not builtupdated Oct 2025 | Jan 2023 | granted Apr 2024 | Oct 2025 | Test Valley | 5.3 |
| Upton Lane, Nurslingbattery storage | battery storage | 99.9 | approved, not builtupdated Jun 2025 | Oct 2024 | granted May 2025 | Jun 2025 | Test Valley | 5.7 |
| Upton Lane, Nurslingbattery storage | battery storage | 50 | approved, not built may be out of dateupdated Aug 2025 | Sep 2021 | granted Jan 2022 | Aug 2025 | Test Valley | 5.7 |
| Station Road, Crescent Industrial Estatebattery storage | battery storage | 62 | approved, not builtupdated Mar 2026 | May 2025 | granted Jan 2026 | Mar 2026 | Test Valley | 6.0 |
| Mill Lane, Nurslingbattery storage | battery storage | 20 | under constructionupdated Mar 2022 | Nov 2019 | granted May 2020 | Mar 2022 | Test Valley | 6.2 |
| Tesco Distribution, Canberra Roadrooftop solar | rooftop solar | 2.1 | application withdrawnupdated Nov 2024 | Oct 2024 | — | Nov 2024 | Test Valley | 6.3 |
| Station Roadbattery storage | battery storage | 49.5 | application withdrawnupdated Nov 2018 | May 2017 | — | Nov 2018 | Test Valley | 6.6 |
| Testwood Water Supply Workssolar farm | solar farm | 1.9 | operationalupdated Sep 2017 | Jul 2016 | granted Dec 2016 | Sep 2017 | New Forest | 7.1 |
| Home Farm, Hursley Park Roadsolar farm | solar farm | 5 | approved, not builtupdated Jul 2025 | Oct 2024 | granted Jun 2025 | Jul 2025 | Winchester | 7.2 |
| Field House Solar / Hursley Roadsolar farm | solar farm | 6.4 | operationalupdated Sep 2018 | Apr 2014 | granted Jul 2014 | Sep 2018 | Winchester | 8.0 |
| IBM Hursleybattery storage | battery storage | 1.5 | approved, not builtupdated Jul 2024 | Mar 2024 | granted Jun 2024 | Jul 2024 | Winchester | 8.3 |
| Thornlands Farm, Fletchwood Road Solar Farmsolar farm | solar farm | 12 | refusedupdated Jul 2024 | Feb 2024 | refused Jun 2024 | Jul 2024 | New Forest | 9.4 |
| Land South Of Carlton Housesolar farm | solar farm | 2.2 | refusedupdated Jan 2016 | Oct 2015 | refused Dec 2015 | Jan 2016 | New Forest | 9.5 |
| Fletchwood Lane, Totton Solar Parksolar farm | solar farm | 5.3 | refusedupdated May 2026 | Jul 2025 | refused Mar 2026 | May 2026 | New Forest | 10.0 |
Smaller schemes under 1 MW, mostly rooftop solar (12)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Woodington Road, East Wellowrooftop solar | rooftop solar | 0.5 | approved, not builtupdated Aug 2022 | Jul 2022 | granted Sep 2022 | Aug 2022 | Test Valley | 4.1 |
| Woodington Solar Farm (Central)solar farm | solar farm | — | under constructionupdated Apr 2020 | Apr 2020 | granted May 2021 | Apr 2020 | Test Valley | 4.6 |
| Mauretania Road, Nurslingrooftop solar | rooftop solar | 0.2 | application submitted may be out of dateupdated Jul 2023 | Jul 2023 | — | Jul 2023 | Test Valley | 6.4 |
| Asquith Nursery, David Lloyd Leisurerooftop solar | rooftop solar | 0.3 | approved, not builtupdated Feb 2024 | Dec 2023 | granted Jan 2024 | Feb 2024 | Test Valley | 7.2 |
| Test Valley Business Centre, Test Lanerooftop solar | rooftop solar | 0.3 | approved, not builtupdated Nov 2022 | Oct 2022 | granted Nov 2022 | Nov 2022 | Southampton | 7.7 |
| Cooper Vision, Speedwell Closerooftop solar | rooftop solar | 0.6 | approved, not builtupdated Nov 2024 | Aug 2024 | granted Oct 2024 | Nov 2024 | Eastleigh | 8.2 |
| Unit 2b, School Lanerooftop solar | rooftop solar | 0.3 | approved, not builtupdated Jun 2023 | May 2023 | granted Jun 2023 | Jun 2023 | Eastleigh | 8.2 |
| Morrisons Supermarket, Tottonrooftop solar | rooftop solar | 0.3 | approved, not builtupdated Oct 2022 | Sep 2022 | granted Oct 2022 | Oct 2022 | New Forest | 8.3 |
| IBM Hursleysolar farm | solar farm | — | approved, not builtupdated Jul 2024 | Mar 2024 | granted Jun 2024 | Jul 2024 | Winchester | 8.3 |
| Southampton General Hospital, Tremona Roadrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Feb 2024 | Dec 2023 | granted Feb 2024 | Feb 2024 | Southampton | 8.5 |
| Spire Hospital, Chalybeate Closerooftop solar | rooftop solar | 0.2 | approved, not builtupdated May 2024 | Mar 2024 | granted May 2024 | May 2024 | Southampton | 8.8 |
| Chandlers Fordrooftop solar | rooftop solar | 0.2 | approved, not builtupdated May 2022 | May 2022 | granted Jun 2022 | May 2022 | Eastleigh | 8.9 |
Distance from the average position of the SO51 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.
By type
| Type | All | Pending | Approved | Operational | Refused | MW in pipeline |
|---|---|---|---|---|---|---|
| Solar farm | 13 | 0 | 4 | 5 | 3 | 51 |
| Rooftop solar | 11 | 1 | 9 | 0 | 0 | 3.3 |
| Battery storage | 7 | 0 | 6 | 0 | 0 | 293 |
MW in pipeline: pending, approved and under-construction capacity.
How Test Valley decides solar, wind and battery applications
| Applications | Test Valley | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 49 | 10,236 |
| Refused | 8 (16%) | 19% |
| Solar refused | 7 of 41 | 12% |
| Onshore wind refused | 0 of 1 | 45% |
| Battery storage refused | 1 of 7 | 16% |
| Median time from submission to decision | 23.6 weeks | 17.0 weeks |
| Appeals lodged / allowed | 4 / 3 | — |
Is the status up to date?
32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near SO51, 2 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.