Energy Projects Near You

Field House Solar / Hursley Road (6.4 MW)

Field House Solar / Hursley Road is a 6.4 MW solar farm project in Winchester, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 24 March 2015; the record was last updated on 4 September 2018.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

6.4 MWsolar farm
operationalstatus in REPD
4 September 2018record last updated
Winchestercouncil area

Planning timeline

DateStage
3 April 2014Application submitted
4 July 2014Planning permission granted
1 January 2015Construction started
24 March 2015Operational

Project details

Technology
solar farm
Capacity
6.4 MW
Status (REPD)
operational
Record last updated
4 September 2018
Operator or applicant
Foresight
Planning authority
Winchester
Planning application reference
14/00813/FUL
Site area
15.3 ha
Address (REPD)
Field House Farm, Hursley, Winchester
Council area (by location)
Winchester
Time to decision
13 weeks
REPD reference
2026

Who decides

ApplicationsWinchesterUK
Decided applications (solar, wind, battery)3710,236
Refused4 (11%)19%
Solar refused0 of 2412%
Onshore wind refused3 of 345%
Battery storage refused1 of 1016%
Median time from submission to decision14.7 weeks17.0 weeks
Appeals lodged / allowed3 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Silkstead Farm, Poles Lanebattery storage49.9approved, not built2.2
Home Farm, Hursley Park Roadsolar farm5approved, not built2.5
Churchers Common Solar Parksolar farm5abandoned3.0
Winchester Battery Storagebattery storage19operational3.6
Misslebrook Farm, Botley Roadbattery storage60approved, not built4.7
South Lynch Farm Solar Farmsolar farm20approved, not built5.7
Grove Solar Park (Phase 2)solar farm11operational7.9
Grove Solar Park (Phase 1)solar farm5operational7.9
Allington Lane Solar & Battery Farmsolar farm27approved, not built7.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.0087, -1.3915).