South Lynch Farm Solar Farm (20 MW)

South Lynch Farm Solar Farm is a 20 MW solar farm project in Winchester, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 17 October 2024, not yet built; the record was last updated on 20 February 2026.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

20 MWsolar farm
approved, not builtstatus in REPD
20 February 2026record last updated
Winchestercouncil area

Planning timeline

DateStage
25 April 2023Application submitted
17 October 2024Planning permission granted
17 October 2027Permission due to expire (unless work starts)

Project details

Technology
solar farm
Capacity
20 MW
Status (REPD)
approved, not built
Record last updated
20 February 2026
Operator or applicant
Novus Renewable Services Limited
Planning authority
Winchester
Planning application reference
23/01025/FUL
Site area
24.1 ha
Address (REPD)
N/O South Lynch Farm
Council area (by location)
Winchester
Time to decision
77 weeks
Contracts for Difference
AR7a
Name in REPD
South Lynch Farm - Solar Farm
REPD reference
13790

Who decides

ApplicationsWinchesterUK
Decided applications (solar, wind, battery)3710,236
Refused4 (11%)19%
Solar refused0 of 2412%
Onshore wind refused3 of 345%
Battery storage refused1 of 1016%
Median time from submission to decision14.7 weeks17.0 weeks
Appeals lodged / allowed3 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Winchester Battery Storagebattery storage19operational3.2
Home Farm, Hursley Park Roadsolar farm5approved, not built3.9
Stockbridge Roadbattery storage10approved, not built4.0
Silkstead Farm, Poles Lanebattery storage49.9approved, not built5.0
Field House Solar / Hursley Roadsolar farm6.4operational5.7
Three Maids Hill Solar Farmsolar farm25operational6.8
Churchers Common Solar Parksolar farm5abandoned7.7
Somborne Park Roadsolar farm5refused7.9
Misslebrook Farm, Botley Roadbattery storage60approved, not built9.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.0601, -1.3936).