Winchester Battery Storage (19 MW)

Winchester Battery Storage is a 19 MW battery storage project in Winchester, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 1 May 2023; the record was last updated on 9 March 2026.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

19 MWbattery storage
operationalstatus in REPD
9 March 2026record last updated
Winchestercouncil area

Planning timeline

DateStage
7 April 2017Application submitted
23 June 2017Planning permission granted
1 May 2023Operational

Project details

Technology
battery storage (stand-alone storage)
Capacity
19 MW
Status (REPD)
operational
Record last updated
9 March 2026
Operator or applicant
Conrad Energy
Planning authority
Winchester
Planning application reference
17/01044/FUL
Address (REPD)
Down Farm Port Lane Hursley
Council area (by location)
Winchester
Time to decision
11 weeks
REPD reference
20401

Who decides

ApplicationsWinchesterUK
Decided applications (solar, wind, battery)3710,236
Refused4 (11%)19%
Solar refused0 of 2412%
Onshore wind refused3 of 345%
Battery storage refused1 of 1016%
Median time from submission to decision14.7 weeks17.0 weeks
Appeals lodged / allowed3 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Silkstead Farm, Poles Lanebattery storage49.9approved, not built2.0
South Lynch Farm Solar Farmsolar farm20approved, not built3.2
Home Farm, Hursley Park Roadsolar farm5approved, not built3.4
Field House Solar / Hursley Roadsolar farm6.4operational3.6
Stockbridge Roadbattery storage10approved, not built5.0
Churchers Common Solar Parksolar farm5abandoned6.4
Misslebrook Farm, Botley Roadbattery storage60approved, not built8.2
Three Maids Hill Solar Farmsolar farm25operational8.6
Allington Lane Solar & Battery Farmsolar farm27approved, not built9.3

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.0369, -1.3668).