Energy Projects Near You

Silkstead Farm, Poles Lane (49.9 MW battery storage)

Silkstead Farm, Poles Lane is a 49.9 MW battery storage project in Winchester, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 13 March 2025, not yet built; the record was last updated on 2 December 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

49.9 MWbattery storage
approved, not builtstatus in REPD
2 December 2025record last updated
Winchestercouncil area

Planning timeline

DateStage
5 June 2024Application submitted
13 March 2025Planning permission granted

Project details

Technology
battery storage (stand-alone storage)
Capacity
49.9 MW
Status (REPD)
approved, not built
Record last updated
2 December 2025
Operator or applicant
Winchester Energy Reserve Limited
Planning authority
Winchester
Planning application reference
24/01007/FUL
Address (REPD)
Silkstead Farm, Poles Lane, Hursley, Winchester
Council area (by location)
Winchester
Time to decision
40 weeks
Name in REPD
Silkstead Farm, Poles Lane - Battery Energy Storage System
REPD reference
15674

Who decides

ApplicationsWinchesterUK
Decided applications (solar, wind, battery)3710,236
Refused4 (11%)19%
Solar refused0 of 2412%
Onshore wind refused3 of 345%
Battery storage refused1 of 1016%
Median time from submission to decision14.7 weeks17.0 weeks
Appeals lodged / allowed3 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Winchester Battery Storagebattery storage19operational2.0
Field House Solar / Hursley Roadsolar farm6.4operational2.2
Home Farm, Hursley Park Roadsolar farm5approved, not built3.4
South Lynch Farm Solar Farmsolar farm20approved, not built5.0
Churchers Common Solar Parksolar farm5abandoned5.2
Misslebrook Farm, Botley Roadbattery storage60approved, not built6.8
Stockbridge Roadbattery storage10approved, not built6.9
Allington Lane Solar & Battery Farmsolar farm27approved, not built7.5
Chalcroft Solar Parksolar farm6.3operational8.7

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.019, -1.365).