Solar, wind and battery projects near Eastleigh (SO50)
53 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of SO50 (Eastleigh): 4 are waiting for a planning decision, 36 approved but not yet running, 8 operational. The largest live scheme is Upton Lane, Nursling (99.9 MW battery storage, approved on 15 May 2025, not yet built), 9.5 km away. Source: Renewable Energy Planning Database, July 2026 extract.
Projects within 10 km of SO50
Projects of 1 MW and more (23)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Solarsolar | solar | 1 | abandonedupdated Jul 2019 | Oct 2013 | granted Mar 2014 | Jul 2019 | Eastleigh | 0.8 |
| Allington Lane Solar & Battery Farmsolar farm | solar farm | 27 | approved, not builtupdated Jul 2025 | Dec 2023 | granted Jul 2024 | Jul 2025 | Eastleigh | 2.6 |
| Allington Lane Solar & Battery Farmbattery storage | battery storage | 16 | approved, not builtupdated Jul 2025 | Dec 2023 | granted Jul 2024 | Jul 2025 | Eastleigh | 2.6 |
| Chalcroft Solar Parksolar farm | solar farm | 6.3 | operationalupdated Apr 2013 | Sep 2012 | granted Dec 2012 | Apr 2013 | Eastleigh | 3.2 |
| Lower Russells Fieldsolar | solar | 1 | permission expiredupdated Sep 2017 | Dec 2013 | granted May 2014 | Sep 2017 | Eastleigh | 3.3 |
| Field House Solar / Hursley Roadsolar farm | solar farm | 6.4 | operationalupdated Sep 2018 | Apr 2014 | granted Jul 2014 | Sep 2018 | Winchester | 5.7 |
| Silkstead Farm, Poles Lanebattery storage | battery storage | 49.9 | approved, not builtupdated Dec 2025 | Jun 2024 | granted Mar 2025 | Dec 2025 | Winchester | 5.8 |
| Misslebrook Farm, Botley Roadbattery storage | battery storage | 60 | approved, not builtupdated Oct 2025 | Jan 2023 | granted Apr 2024 | Oct 2025 | Test Valley | 6.6 |
| Churchers Common Solar Parksolar farm | solar farm | 5 | abandonedupdated Oct 2018 | Jun 2015 | granted Dec 2015 | Oct 2018 | Test Valley | 6.8 |
| IBM Hursleybattery storage | battery storage | 1.5 | approved, not builtupdated Jul 2024 | Mar 2024 | granted Jun 2024 | Jul 2024 | Winchester | 7.2 |
| Winchester Battery Storagebattery storage | battery storage | 19 | operationalupdated Mar 2026 | Apr 2017 | granted Jun 2017 | Mar 2026 | Winchester | 7.8 |
| Butts Field, Mill Lanebattery storage | battery storage | 99 | approved, not builtupdated May 2025 | Nov 2023 | granted Oct 2024 | May 2025 | Southampton | 8.1 |
| Home Farm, Hursley Park Roadsolar farm | solar farm | 5 | approved, not builtupdated Jul 2025 | Oct 2024 | granted Jun 2025 | Jul 2025 | Winchester | 8.2 |
| Weston Lanebattery storage | battery storage | 49.9 | refusedupdated Jul 2025 | Nov 2023 | refused Jun 2025 | Jul 2025 | Southampton | 8.6 |
| Netley Landfill Solarsolar farm | solar farm | 12 | operationalupdated Sep 2018 | Aug 2014 | granted Oct 2014 | Sep 2018 | Eastleigh | 8.7 |
| New Farm House Locks Farmsolar farm | solar farm | 18 | approved, not built may be out of dateupdated Oct 2024 | Jun 2021 | granted Jun 2023 | Oct 2024 | Winchester | 9.1 |
| Upton Lane, Nurslingbattery storage | battery storage | 99.9 | approved, not builtupdated Jun 2025 | Oct 2024 | granted May 2025 | Jun 2025 | Test Valley | 9.5 |
| Upton Lane, Nurslingbattery storage | battery storage | 50 | approved, not built may be out of dateupdated Aug 2025 | Sep 2021 | granted Jan 2022 | Aug 2025 | Test Valley | 9.5 |
| Raglington Farmsolar farm | solar farm | 5.8 | operationalupdated Jul 2018 | Apr 2012 | granted Jul 2012 | Jul 2018 | Winchester | 9.5 |
| Bishop’s Waltham Solar Farmsolar farm | solar farm | 12 | operationalupdated May 2017 | Apr 2015 | granted Aug 2015 | May 2017 | Winchester | 9.7 |
| Grove Solar Park (Phase 2)solar farm | solar farm | 11 | operationalupdated Jan 2017 | Jul 2014 | granted Sep 2015 | Jan 2017 | Test Valley | 9.7 |
| Grove Solar Park (Phase 1)solar farm | solar farm | 5 | operationalupdated Jul 2016 | Jul 2014 | granted Sep 2015 | Jul 2016 | Test Valley | 9.7 |
| Glebe Farm, Curdridge Lane Solar Farmsolar farm | solar farm | 10 | application submittedupdated Jul 2025 | May 2025 | — | Jul 2025 | Winchester | 9.7 |
Smaller schemes under 1 MW, mostly rooftop solar (30)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Pei Genesis UK Limited, George Curl Wayrooftop solar | rooftop solar | 0.3 | approved, not builtupdated Feb 2023 | Dec 2022 | granted Jan 2023 | Feb 2023 | Eastleigh | 2.9 |
| Airways Distribution Park, Wide Lane, Unit 1rooftop solar | rooftop solar | 0.5 | approved, not builtupdated Feb 2025 | Dec 2024 | granted Jan 2025 | Feb 2025 | Southampton | 3.1 |
| Airways Distribution Park, Wide Lanerooftop solar | rooftop solar | 0.3 | approved, not builtupdated Jun 2023 | Apr 2023 | granted Jun 2023 | Jun 2023 | Southampton | 3.1 |
| Chandlers Fordrooftop solar | rooftop solar | 0.2 | approved, not builtupdated May 2022 | May 2022 | granted Jun 2022 | May 2022 | Eastleigh | 3.3 |
| Allington Lane, West Endrooftop solar | rooftop solar | 0.5 | approved, not builtupdated Nov 2021 | Oct 2021 | granted Nov 2021 | Nov 2021 | Eastleigh | 3.3 |
| Itchen Power, West Endsolar farm | solar farm | 0.2 | approved, not built may be out of dateupdated Oct 2021 | Oct 2021 | granted Jan 2022 | Oct 2021 | Eastleigh | 3.4 |
| Cooper Vision, Speedwell Closerooftop solar | rooftop solar | 0.6 | approved, not builtupdated Nov 2024 | Aug 2024 | granted Oct 2024 | Nov 2024 | Eastleigh | 3.6 |
| Unit 2b, School Lanerooftop solar | rooftop solar | 0.3 | approved, not builtupdated Jun 2023 | May 2023 | granted Jun 2023 | Jun 2023 | Eastleigh | 3.7 |
| Holiday Inn Express, Botley Roadrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Jun 2025 | Apr 2025 | granted May 2025 | Jun 2025 | Eastleigh | 4.8 |
| Utilita Bowl, Marshall Driverooftop solar | rooftop solar | 0.4 | approved, not builtupdated Jun 2024 | Mar 2024 | granted May 2024 | Jun 2024 | Eastleigh | 5.2 |
| Sainsbury Supermarket, Tollbar Wayrooftop solar | rooftop solar | 0.8 | approved, not builtupdated Apr 2025 | Jan 2025 | granted Mar 2025 | Apr 2025 | Eastleigh | 5.5 |
| Grosvenor House & Belmont House, Portswood Roadrooftop solar | rooftop solar | 0.2 | approved, not builtupdated May 2025 | Feb 2025 | granted Apr 2025 | May 2025 | Southampton | 5.7 |
| Strategic Park, Comines Wayrooftop solar | rooftop solar | 0.4 | application submitted may be out of dateupdated Oct 2022 | Oct 2022 | — | Oct 2022 | Eastleigh | 6.0 |
| Unit 1, Strategic Park, Comines Wayrooftop solar | rooftop solar | 0.3 | approved, not builtupdated Sep 2022 | Aug 2022 | granted Sep 2022 | Sep 2022 | Eastleigh | 6.0 |
| Unit 2 To 5, Hazeley Enterprise Parkrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Jun 2022 | May 2022 | granted Jul 2022 | Jun 2022 | Winchester | 6.6 |
| Antelope Retail Park, Bursledon Roadrooftop solar | rooftop solar | 0.7 | approved, not builtupdated Jun 2026 | Feb 2026 | granted Apr 2026 | Jun 2026 | Southampton | 7.0 |
| Shamrock Quay Solar Photovoltaic Equipmentrooftop solar | rooftop solar | — | refusedupdated May 2021 | Mar 2021 | refused Apr 2021 | May 2021 | Southampton | 7.1 |
| IBM Hursleysolar farm | solar farm | — | approved, not builtupdated Jul 2024 | Mar 2024 | granted Jun 2024 | Jul 2024 | Winchester | 7.2 |
| Saxon House, Lower York Streetrooftop solar | rooftop solar | — | approved, not builtupdated May 2021 | Mar 2021 | granted May 2021 | May 2021 | Southampton | 7.3 |
| Southampton General Hospital, Tremona Roadrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Feb 2024 | Dec 2023 | granted Feb 2024 | Feb 2024 | Southampton | 7.6 |
| Spire Hospital, Chalybeate Closerooftop solar | rooftop solar | 0.2 | approved, not builtupdated May 2024 | Mar 2024 | granted May 2024 | May 2024 | Southampton | 7.7 |
| Sainsburys Supermarkets, Badger Farm Roadrooftop solar | rooftop solar | 0.6 | approved, not builtupdated Jun 2024 | May 2024 | granted Jun 2024 | Jun 2024 | Winchester | 8.6 |
| Harbour Parade Solar Photovoltaicsrooftop solar | rooftop solar | — | approved, not builtupdated Aug 2025 | Jun 2025 | granted Jul 2025 | Aug 2025 | Southampton | 8.7 |
| West Quay Retail Park, Harbour Paraderooftop solar | rooftop solar | — | approved, not builtupdated Jan 2026 | Oct 2025 | granted Dec 2025 | Jan 2026 | Southampton | 8.7 |
| Lucia Foster Welch Student Hall Of Residencerooftop solar | rooftop solar | — | approved, not built may be out of dateupdated Oct 2022 | Jul 2022 | granted Sep 2022 | Oct 2022 | Southampton | 8.7 |
| Buildings J K And Z Tesla Centre, Herbert Walker Avenuerooftop solar | rooftop solar | 0.8 | approved, not builtupdated Jan 2023 | Nov 2022 | granted Jan 2023 | Jan 2023 | Southampton | 9.3 |
| Asquith Nursery, David Lloyd Leisurerooftop solar | rooftop solar | 0.3 | approved, not builtupdated Feb 2024 | Dec 2023 | granted Jan 2024 | Feb 2024 | Test Valley | 9.4 |
| Glebe Farm, Curdridge Lanebattery storage | battery storage | — | application submittedupdated Jul 2025 | May 2025 | — | Jul 2025 | Winchester | 9.7 |
| Winchester Sport And Leisure Park, Bar End Roadrooftop solar | rooftop solar | 0.2 | application submitted | Apr 2026 | — | — | Winchester | 9.8 |
| National Air Traffic Services, Sopwith Wayrooftop solar | rooftop solar | 1 | approved, not builtupdated Sep 2023 | Jul 2023 | granted Aug 2023 | Sep 2023 | Fareham | 9.9 |
Distance from the average position of the SO50 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.
By type
| Type | All | Pending | Approved | Operational | Refused | MW in pipeline |
|---|---|---|---|---|---|---|
| Solar farm | 14 | 1 | 5 | 7 | 0 | 60.2 |
| Rooftop solar | 27 | 2 | 24 | 0 | 1 | 9.4 |
| Solar | 2 | 0 | 0 | 0 | 0 | 0 |
| Battery storage | 10 | 1 | 7 | 1 | 1 | 376 |
MW in pipeline: pending, approved and under-construction capacity.
How Eastleigh decides solar, wind and battery applications
| Applications | Eastleigh | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 19 | 10,236 |
| Refused | 0 (0%) | 19% |
| Solar refused | 0 of 17 | 12% |
| Battery storage refused | 0 of 2 | 16% |
| Median time from submission to decision | 10.3 weeks | 17.0 weeks |
| Appeals lodged / allowed | 0 / 0 | — |
Is the status up to date?
32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near SO50, 5 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.