Netley Landfill Solar (12 MW)

Netley Landfill Solar is a 12 MW solar farm project in Eastleigh, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 31 March 2017; the record was last updated on 1 September 2018.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

12 MWsolar farm
operationalstatus in REPD
1 September 2018record last updated
Eastleighcouncil area

Planning timeline

DateStage
5 August 2014Application submitted
30 October 2014Planning permission granted
1 January 2017Construction started
31 March 2017Operational

Project details

Technology
solar farm
Capacity
12 MW
Status (REPD)
operational
Record last updated
1 September 2018
Operator or applicant
REG Solarpower/Veolia
Planning authority
Eastleigh
Planning application reference
F/14/75012
Site area
35.0 ha
Address (REPD)
Netley Landfill Site Portsmouth Road Netley Southampton
Council area (by location)
Eastleigh
Time to decision
12 weeks
Contracts for Difference
AR1
REPD reference
2044

Who decides

ApplicationsEastleighUK
Decided applications (solar, wind, battery)1910,236
Refused0 (0%)19%
Solar refused0 of 1712%
Battery storage refused0 of 216%
Median time from submission to decision10.3 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Butts Field, Mill Lanebattery storage99approved, not built1.0
Hamble Lane Battery Energy Storagebattery storage6approved, not built1.4
Weston Lanebattery storage49.9refused1.7
Chalcroft Solar Parksolar farm6.3operational6.8
East Road, Marchwoodbattery storage200approved, not built7.5
Raglington Farmsolar farm5.8operational7.7
Funtley Refuse Tipsolar farm10permission expired8.0
Funtley Solar Photovoltaic PV Farmsolar farm10.5application submitted8.0
Ash Farm, Titchfield Lanebattery storage15approved, not built8.1

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (50.8905, -1.333).