Solar, wind and battery projects near Winchester (SO23)
15 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of SO23 (Winchester): 1 is waiting for a planning decision, 9 approved but not yet running, 3 operational. The largest live scheme is Silkstead Farm, Poles Lane (49.9 MW battery storage, approved on 13 March 2025, not yet built), 6.8 km away. Source: Renewable Energy Planning Database, July 2026 extract.
Projects within 10 km of SO23
Projects of 1 MW and more (9)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Stockbridge Roadbattery storage | battery storage | 10 | approved, not built may be out of dateupdated Feb 2020 | Oct 2017 | granted Dec 2017 | Feb 2020 | Winchester | 2.9 |
| Winchester Battery Storagebattery storage | battery storage | 19 | operationalupdated Mar 2026 | Apr 2017 | granted Jun 2017 | Mar 2026 | Winchester | 5.4 |
| Three Maids Hill Solar Farmsolar farm | solar farm | 25 | operationalupdated Jan 2024 | Oct 2020 | granted May 2021 | Jan 2024 | Winchester | 5.7 |
| South Lynch Farm Solar Farmsolar farm | solar farm | 20 | approved, not builtupdated Feb 2026 | Apr 2023 | granted Oct 2024 | Feb 2026 | Winchester | 6.0 |
| Sparsholt collegebattery storage | battery storage | 2 | permission expiredupdated Aug 2020 | Sep 2017 | granted Dec 2017 | Aug 2020 | Winchester | 6.3 |
| Silkstead Farm, Poles Lanebattery storage | battery storage | 49.9 | approved, not builtupdated Dec 2025 | Jun 2024 | granted Mar 2025 | Dec 2025 | Winchester | 6.8 |
| IBM Hursleybattery storage | battery storage | 1.5 | approved, not builtupdated Jul 2024 | Mar 2024 | granted Jun 2024 | Jul 2024 | Winchester | 7.7 |
| Home Farm, Hursley Park Roadsolar farm | solar farm | 5 | approved, not builtupdated Jul 2025 | Oct 2024 | granted Jun 2025 | Jul 2025 | Winchester | 8.6 |
| Field House Solar / Hursley Roadsolar farm | solar farm | 6.4 | operationalupdated Sep 2018 | Apr 2014 | granted Jul 2014 | Sep 2018 | Winchester | 8.8 |
Smaller schemes under 1 MW, mostly rooftop solar (6)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Micheldever Tyres Winchester, Winnall Warehouserooftop solar | rooftop solar | — | approved, not builtupdated Apr 2026 | Dec 2025 | granted Jan 2026 | Apr 2026 | Winchester | 0.9 |
| Winchester Sport And Leisure Park, Bar End Roadrooftop solar | rooftop solar | 0.2 | application submitted | Apr 2026 | — | — | Winchester | 1.6 |
| Sainsburys Supermarkets, Badger Farm Roadrooftop solar | rooftop solar | 0.6 | approved, not builtupdated Jun 2024 | May 2024 | granted Jun 2024 | Jun 2024 | Winchester | 3.3 |
| Unit 2 To 5, Hazeley Enterprise Parkrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Jun 2022 | May 2022 | granted Jul 2022 | Jun 2022 | Winchester | 5.2 |
| Three Maids Hill Solar Farmbattery storage | battery storage | — | abandonedupdated Jul 2024 | Oct 2020 | granted May 2021 | Jul 2024 | Winchester | 5.9 |
| IBM Hursleysolar farm | solar farm | — | approved, not builtupdated Jul 2024 | Mar 2024 | granted Jun 2024 | Jul 2024 | Winchester | 7.7 |
Distance from the average position of the SO23 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.
By type
| Type | All | Pending | Approved | Operational | Refused | MW in pipeline |
|---|---|---|---|---|---|---|
| Solar farm | 5 | 0 | 3 | 2 | 0 | 25 |
| Rooftop solar | 4 | 1 | 3 | 0 | 0 | 1 |
| Battery storage | 6 | 0 | 3 | 1 | 0 | 61.4 |
MW in pipeline: pending, approved and under-construction capacity.
How Winchester decides solar, wind and battery applications
| Applications | Winchester | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 37 | 10,236 |
| Refused | 4 (11%) | 19% |
| Solar refused | 0 of 24 | 12% |
| Onshore wind refused | 3 of 3 | 45% |
| Battery storage refused | 1 of 10 | 16% |
| Median time from submission to decision | 14.7 weeks | 17.0 weeks |
| Appeals lodged / allowed | 3 / 0 | — |
Is the status up to date?
32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near SO23, 1 project has a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.