Renewable energy projects in Southampton

15 solar, wind or battery projects of 150 kW or more are located in Southampton (REPD, July 2026 extract): 0 pending, 13 approved but not running, 0 operational and 2 refused. The council refused 2 of 16 decided applications (12%; UK 19%), with a median 8 weeks from submission to decision.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

15projects in the council area
0awaiting a decision
13approved, not running
12%of decisions refused

How Southampton decides

ApplicationsSouthamptonUK
Decided applications (solar, wind, battery)1610,236
Refused2 (12%)19%
Solar refused1 of 1412%
Battery storage refused1 of 216%
Median time from submission to decision7.8 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

Projects in Southampton

Projects of 1 MW and more (2)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updated
Butts Field, Mill Lanebattery storagebattery storage99approved, not builtupdated May 2025Nov 2023granted Oct 2024May 2025
Weston Lanebattery storagebattery storage49.9refusedupdated Jul 2025Nov 2023refused Jun 2025Jul 2025
Smaller schemes under 1 MW, mostly rooftop solar (13)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updated
Buildings J K And Z Tesla Centre, Herbert Walker Avenuerooftop solarrooftop solar0.8approved, not builtupdated Jan 2023Nov 2022granted Jan 2023Jan 2023
Antelope Retail Park, Bursledon Roadrooftop solarrooftop solar0.7approved, not builtupdated Jun 2026Feb 2026granted Apr 2026Jun 2026
Airways Distribution Park, Wide Lane, Unit 1rooftop solarrooftop solar0.5approved, not builtupdated Feb 2025Dec 2024granted Jan 2025Feb 2025
Airways Distribution Park, Wide Lanerooftop solarrooftop solar0.3approved, not builtupdated Jun 2023Apr 2023granted Jun 2023Jun 2023
Test Valley Business Centre, Test Lanerooftop solarrooftop solar0.3approved, not builtupdated Nov 2022Oct 2022granted Nov 2022Nov 2022
Southampton General Hospital, Tremona Roadrooftop solarrooftop solar0.2approved, not builtupdated Feb 2024Dec 2023granted Feb 2024Feb 2024
Spire Hospital, Chalybeate Closerooftop solarrooftop solar0.2approved, not builtupdated May 2024Mar 2024granted May 2024May 2024
Grosvenor House & Belmont House, Portswood Roadrooftop solarrooftop solar0.2approved, not builtupdated May 2025Feb 2025granted Apr 2025May 2025
Shamrock Quay Solar Photovoltaic Equipmentrooftop solarrooftop solar—refusedupdated May 2021Mar 2021refused Apr 2021May 2021
Saxon House, Lower York Streetrooftop solarrooftop solar—approved, not builtupdated May 2021Mar 2021granted May 2021May 2021
Lucia Foster Welch Student Hall Of Residencerooftop solarrooftop solar—approved, not built may be out of dateupdated Oct 2022Jul 2022granted Sep 2022Oct 2022
Harbour Parade Solar Photovoltaicsrooftop solarrooftop solar—approved, not builtupdated Aug 2025Jun 2025granted Jul 2025Aug 2025
West Quay Retail Park, Harbour Paraderooftop solarrooftop solar—approved, not builtupdated Jan 2026Oct 2025granted Dec 2025Jan 2026

Postcode districts in Southampton

DistrictProjects within 10 kmPendingApprovedOperational
SO14613416
SO15613397
SO16613388
SO17623417
SO18633438
SO19644474

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Projects belong to Southampton by location (nearest postcode to the REPD grid reference); decisions are counted by the planning authority named in REPD.