Energy Projects Near You

Renewable energy projects in Basingstoke and Deane

36 solar, wind or battery projects of 150 kW or more are located in Basingstoke and Deane (REPD, July 2026 extract): 4 pending, 20 approved but not running, 7 operational and 4 refused. The council refused 8 of 30 decided applications (27%; UK 19%), with a median 26 weeks from submission to decision.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

36projects in the council area
4awaiting a decision
20approved, not running
27%of decisions refused

How Basingstoke and Deane decides

ApplicationsBasingstoke and DeaneUK
Decided applications (solar, wind, battery)3010,236
Refused8 (27%)19%
Solar refused5 of 2212%
Onshore wind refused1 of 145%
Battery storage refused2 of 716%
Median time from submission to decision26.3 weeks17.0 weeks
Appeals lodged / allowed4 / 5—

Projects in Basingstoke and Deane

Projects of 1 MW and more (21)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updated
Frog Lane, Little Londonbattery storagebattery storage115refusedupdated Jun 2026Apr 2025refused May 2026Jun 2026
Minchens Lane Battery Storage Facilitybattery storagebattery storage100operationalupdated Mar 2026Jan 2021granted Oct 2021Mar 2026
Ash Lane, Little Londonbattery storagebattery storage57approved, not builtupdated Apr 2022Jun 2022granted Feb 2023Apr 2022
Withy Place, Bramley Roadbattery storagebattery storage50approved, not builtupdated Jul 2025Sep 2024granted Jul 2025Jul 2025
Bramley Frith Solar Farmsolar farmsolar farm49.9approved, not built may be out of dateupdated Sep 2020Dec 2020granted Feb 2023Sep 2020
Hook Lane, Malshangersolar farmsolar farm30approved, not builtupdated May 2026Dec 2023granted Feb 2026May 2026
Preston Farm, Preston Candoversolar farmsolar farm28approved, not builtupdated Jan 2024Nov 2021granted Sep 2022Jan 2024
Manor Farm, Sherborne Solar Farmsolar farmsolar farm28application submittedupdated Aug 2025Jul 2025—Aug 2025
Strattons Farm, Newbury Road Solar PV Farmsolar farmsolar farm23application submitted may be out of dateupdated May 2024Apr 2024—May 2024
Lower Wyke Farm, St Mary Bourne Solar Farmsolar farmsolar farm21approved, not builtupdated Jul 2026Aug 2023granted Jun 2026Jul 2026
Basing Roadbattery storagebattery storage20application submitted may be out of dateupdated Feb 2023Jul 2021—Feb 2023
Woodmancott Downwind farmwind farm18refusedupdated Jan 2015Jun 2013refused Jun 2014Jan 2015
Chineham Battery Energy Storage Facilitybattery storagebattery storage15application withdrawnupdated Nov 2018Jul 2016—Nov 2018
Beaurepaire Farmsolar farmsolar farm12refusedupdated Sep 2015Jun 2013refused Jan 2014Sep 2015
Upper Farm solar parksolar farmsolar farm12operationalupdated Sep 2015Jun 2013granted Aug 2014Sep 2015
Frying Down Copse Solar Farmsolar farmsolar farm5operationalupdated Oct 2012Feb 2011granted May 2011Oct 2012
Berry Court Farmsolar farmsolar farm4.2operationalupdated Nov 2018Aug 2014granted Apr 2015Nov 2018
Overtonsolar farmsolar farm4operationalupdated Mar 2016Jun 2014granted Dec 2014Mar 2016
Land South of Shothanger Workssolar farmsolar farm3.5refusedupdated Dec 2015Jun 2015refused Nov 2015Dec 2015
Hill End Farmsolar farmsolar farm2.8operationalupdated Aug 2014Jul 2013granted Dec 2013Aug 2014
Berry Court Solar Farmbattery storagebattery storage1operationalupdated Mar 2019Jun 2016—Mar 2019
Smaller schemes under 1 MW, mostly rooftop solar (15)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updated
Sainsburys, Wallop Drive- Solar Panelsrooftop solarrooftop solar0.6approved, not builtupdated Nov 2023Sep 2023granted Nov 2023Nov 2023
Worting Roadrooftop solarrooftop solar0.5approved, not builtupdated Dec 2021Nov 2021granted Feb 2022Dec 2021
Sainsburys, Mulfords Hillrooftop solarrooftop solar0.4approved, not builtupdated Nov 2025Aug 2025granted Oct 2025Nov 2025
Gemini Centre, Hamilton Closerooftop solarrooftop solar0.3approved, not builtupdated May 2023Mar 2023granted May 2023May 2023
Southley Farm Buildings, Overtonrooftop solarrooftop solar0.3approved, not builtupdated Mar 2023Jan 2023granted Mar 2023Mar 2023
Hollywood Bowl, Basingstoke Leisure Park Solar Panel Photovoltaicsrooftop solarrooftop solar0.2approved, not builtupdated May 2022May 2022granted Jul 2022May 2022
Pinewood, Crockford Lanesolar farmsolar farm0.2approved, not builtupdated Feb 2024Dec 2023granted Feb 2024Feb 2024
Worting Roadrooftop solarrooftop solar0.2approved, not builtupdated Nov 2021Sep 2021granted Nov 2021Nov 2021
Inchcape Estates, Edison Roadrooftop solarrooftop solar0.1approved, not builtupdated Jul 2023Jun 2023granted Jul 2023Jul 2023
Bramley Frith Solar Farmbattery storagebattery storage—approved, not built may be out of dateupdated Feb 2021Dec 2020granted Feb 2023Feb 2021
Ash Lane, Little Londonbattery storagebattery storage—approved, not builtupdated May 2025Jan 2024granted Apr 2025May 2025
Brickledons Farm, Clappers Farm Roadbattery storagebattery storage—approved, not builtupdated Mar 2025Nov 2024granted Mar 2025Mar 2025
Lime Tree Way, Crockford Lanesolar farmsolar farm—approved, not builtupdated Jan 2026Jun 2025granted Dec 2025Jan 2026
The Costello Schoolrooftop solarrooftop solar—approved, not builtupdated Nov 2025Jul 2025granted Oct 2025Nov 2025
Popham Logistics Park - Warehouses & Solar Farmsolar farmsolar farm—application submittedupdated May 2026Apr 2026—May 2026

Postcode districts in Basingstoke and Deane

DistrictProjects within 10 kmPendingApprovedOperational
RG21322215
RG22253125
RG23253126
RG24353235
RG25203113
RG26393257
RG2813044

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Projects belong to Basingstoke and Deane by location (nearest postcode to the REPD grid reference); decisions are counted by the planning authority named in REPD.