Frying Down Copse Solar Farm (5 MW)

Frying Down Copse Solar Farm is a 5 MW solar farm project in Basingstoke and Deane, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 16 April 2012; the record was last updated on 15 October 2012.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWsolar farm
operationalstatus in REPD
15 October 2012record last updated
Basingstoke and Deanecouncil area

Planning timeline

DateStage
2 February 2011Application submitted
13 May 2011Planning permission granted
16 April 2012Operational

Project details

Technology
solar farm
Capacity
5 MW
Status (REPD)
operational
Record last updated
15 October 2012
Operator or applicant
Private Developer
Planning authority
Basingstoke and Deane
Planning application reference
BDB/73851
Site area
16.2 ha
Address (REPD)
north of Bushywarren Lane, Ellisfield, Basingstoke
Council area (by location)
Basingstoke and Deane
Time to decision
14 weeks
REPD reference
1342

Who decides

ApplicationsBasingstoke and DeaneUK
Decided applications (solar, wind, battery)3010,236
Refused8 (27%)19%
Solar refused5 of 2212%
Onshore wind refused1 of 145%
Battery storage refused2 of 716%
Median time from submission to decision26.3 weeks17.0 weeks
Appeals lodged / allowed4 / 5—

Other large projects within 10 km

ProjectTypeMWStatuskm
Upper Farm solar parksolar farm12operational5.1
Basing Roadbattery storage20application submitted6.1
Preston Farm, Preston Candoversolar farm28approved, not built7.4
Chineham Battery Energy Storage Facilitybattery storage15application withdrawn8.3
Woodmancott Downwind farm18refused8.4
Chosley Farm, North Warnborough Solar Farm and Battery storagesolar farm49.9approved, not built8.5
Fleet Hill Solar Farmsolar farm47.5under construction9.5
Godsfield Solar Farmsolar farm11.8application withdrawn10.0

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.2142, -1.0694).