Upper Farm solar park (12 MW)

Upper Farm solar park is a 12 MW solar farm project in Basingstoke and Deane, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 30 March 2015; the record was last updated on 30 September 2015.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

12 MWsolar farm
operationalstatus in REPD
30 September 2015record last updated
Basingstoke and Deanecouncil area

Planning timeline

DateStage
13 June 2013Application submitted
15 January 2014Refused by the planning authority
12 August 2014Planning permission granted
12 August 2014Appeal allowed
15 November 2014Construction started
30 March 2015Operational

Project details

Technology
solar farm
Capacity
12 MW
Status (REPD)
operational
Record last updated
30 September 2015
Operator or applicant
Kronos Solar
Planning authority
Basingstoke and Deane
Planning application reference
13/00653/FUL
Appeal reference
14/00023/REF
Address (REPD)
Upper Farm Bradley Alresford Hampshire SO24 9SA
Council area (by location)
Basingstoke and Deane
Time to decision
61 weeks
REPD reference
2082

Who decides

ApplicationsBasingstoke and DeaneUK
Decided applications (solar, wind, battery)3010,236
Refused8 (27%)19%
Solar refused5 of 2212%
Onshore wind refused1 of 145%
Battery storage refused2 of 716%
Median time from submission to decision26.3 weeks17.0 weeks
Appeals lodged / allowed4 / 5—

Other large projects within 10 km

ProjectTypeMWStatuskm
Preston Farm, Preston Candoversolar farm28approved, not built4.3
Godsfield Solar Farmsolar farm11.8application withdrawn4.9
Frying Down Copse Solar Farmsolar farm5operational5.1
Woodmancott Downwind farm18refused5.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.1721, -1.0997).