Energy Projects Near You

Solar, wind and battery projects near Basingstoke (RG24)

35 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of RG24 (Basingstoke and Deane): 3 are waiting for a planning decision, 23 approved but not yet running, 5 operational. The largest live scheme is Ash Lane, Little London (57 MW battery storage, approved on 9 February 2023, not yet built), 6.5 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

35projects within 10 km
3awaiting a decision
23approved, not running
5operational

Projects within 10 km of RG24

Projects of 1 MW and more (19)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Chineham Battery Energy Storage Facilitybattery storagebattery storage15application withdrawnupdated Nov 2018Jul 2016—Nov 2018Basingstoke and Deane0.9
Basing Roadbattery storagebattery storage20application submitted may be out of dateupdated Feb 2023Jul 2021—Feb 2023Basingstoke and Deane1.8
Beaurepaire Farmsolar farmsolar farm12refusedupdated Sep 2015Jun 2013refused Jan 2014Sep 2015Basingstoke and Deane3.9
Manor Farm, Sherborne Solar Farmsolar farmsolar farm28application submittedupdated Aug 2025Jul 2025—Aug 2025Basingstoke and Deane4.0
Hill End Farmsolar farmsolar farm2.8operationalupdated Aug 2014Jul 2013granted Dec 2013Aug 2014Basingstoke and Deane4.1
Land South of Shothanger Workssolar farmsolar farm3.5refusedupdated Dec 2015Jun 2015refused Nov 2015Dec 2015Basingstoke and Deane4.3
Berry Court Solar Farmbattery storagebattery storage1operationalupdated Mar 2019Jun 2016—Mar 2019Basingstoke and Deane5.4
Minchens Lane Battery Storage Facilitybattery storagebattery storage100operationalupdated Mar 2026Jan 2021granted Oct 2021Mar 2026Basingstoke and Deane5.7
Berry Court Farmsolar farmsolar farm4.2operationalupdated Nov 2018Aug 2014granted Apr 2015Nov 2018Basingstoke and Deane5.7
Frog Lane, Little Londonbattery storagebattery storage115refusedupdated Jun 2026Apr 2025refused May 2026Jun 2026Basingstoke and Deane6.1
Bramley Frith Solar Farmsolar farmsolar farm49.9approved, not built may be out of dateupdated Sep 2020Dec 2020granted Feb 2023Sep 2020Basingstoke and Deane6.5
Ash Lane, Little Londonbattery storagebattery storage57approved, not builtupdated Apr 2022Jun 2022granted Feb 2023Apr 2022Basingstoke and Deane6.5
Hook Lane, Malshangersolar farmsolar farm30approved, not builtupdated May 2026Dec 2023granted Feb 2026May 2026Basingstoke and Deane6.8
Withy Place, Bramley Roadbattery storagebattery storage50approved, not builtupdated Jul 2025Sep 2024granted Jul 2025Jul 2025Basingstoke and Deane7.1
Frying Down Copse Solar Farmsolar farmsolar farm5operationalupdated Oct 2012Feb 2011granted May 2011Oct 2012Basingstoke and Deane7.5
Bunkers Hill Farm Solar farm & Battery stationssolar farmsolar farm49.9under constructionupdated Jan 2022Feb 2021granted Nov 2021Jan 2022Hart8.8
Chosley Farm, North Warnborough Solar Farm and Battery storagesolar farmsolar farm49.9approved, not built may be out of dateupdated Feb 2026Jan 2021granted Nov 2021Feb 2026Hart9.1
Holt Lane Solar Parksolar farmsolar farm22application submittedupdated Jun 2025May 2025—Jun 2025Hart9.2
Kiln Fields Solar Farmsolar farmsolar farm17.9under constructionupdated Jan 2024Nov 2021granted Dec 2021Jan 2024Hart9.7
Smaller schemes under 1 MW, mostly rooftop solar (16)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Pinewood, Crockford Lanesolar farmsolar farm0.2approved, not builtupdated Feb 2024Dec 2023granted Feb 2024Feb 2024Basingstoke and Deane1.4
Inchcape Estates, Edison Roadrooftop solarrooftop solar0.1approved, not builtupdated Jul 2023Jun 2023granted Jul 2023Jul 2023Basingstoke and Deane1.9
Gemini Centre, Hamilton Closerooftop solarrooftop solar0.3approved, not builtupdated May 2023Mar 2023granted May 2023May 2023Basingstoke and Deane2.1
The Costello Schoolrooftop solarrooftop solar—approved, not builtupdated Nov 2025Jul 2025granted Oct 2025Nov 2025Basingstoke and Deane2.1
Lime Tree Way, Crockford Lanesolar farmsolar farm—approved, not builtupdated Jan 2026Jun 2025granted Dec 2025Jan 2026Basingstoke and Deane2.3
Worting Roadrooftop solarrooftop solar0.5approved, not builtupdated Dec 2021Nov 2021granted Feb 2022Dec 2021Basingstoke and Deane2.7
Worting Roadrooftop solarrooftop solar0.2approved, not builtupdated Nov 2021Sep 2021granted Nov 2021Nov 2021Basingstoke and Deane2.8
Hollywood Bowl, Basingstoke Leisure Park Solar Panel Photovoltaicsrooftop solarrooftop solar0.2approved, not builtupdated May 2022May 2022granted Jul 2022May 2022Basingstoke and Deane3.2
Bramley Frith Solar Farmbattery storagebattery storage—approved, not built may be out of dateupdated Feb 2021Dec 2020granted Feb 2023Feb 2021Basingstoke and Deane6.5
Ash Lane, Little Londonbattery storagebattery storage—approved, not builtupdated May 2025Jan 2024granted Apr 2025May 2025Basingstoke and Deane6.6
Sainsburys, Wallop Drive- Solar Panelsrooftop solarrooftop solar0.6approved, not builtupdated Nov 2023Sep 2023granted Nov 2023Nov 2023Basingstoke and Deane6.6
Brickledons Farm, Clappers Farm Roadbattery storagebattery storage—approved, not builtupdated Mar 2025Nov 2024granted Mar 2025Mar 2025Basingstoke and Deane8.0
Bunkers Hill Farm Solar farm & Battery stationsbattery storagebattery storage—under constructionupdated Nov 2021Feb 2021granted Nov 2021Nov 2021Hart8.8
Bartley Wood Business Parkrooftop solarrooftop solar0.1approved, not builtupdated Aug 2023May 2023granted Jul 2023Aug 2023Hart8.8
Chosley Farm, North Warnborough Solar Farm and Battery storagebattery storagebattery storage—approved, not built may be out of dateupdated Feb 2026Jan 2021granted Nov 2021Feb 2026Hart9.1
Sainsburys, Mulfords Hillrooftop solarrooftop solar0.4approved, not builtupdated Nov 2025Aug 2025granted Oct 2025Nov 2025Basingstoke and Deane9.3

Distance from the average position of the RG24 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm142732248
Rooftop solar909002.5
Battery storage121721127

MW in pipeline: pending, approved and under-construction capacity.

How Basingstoke and Deane decides solar, wind and battery applications

ApplicationsBasingstoke and DeaneUK
Decided applications (solar, wind, battery)3010,236
Refused8 (27%)19%
Solar refused5 of 2212%
Onshore wind refused1 of 145%
Battery storage refused2 of 716%
Median time from submission to decision26.3 weeks17.0 weeks
Appeals lodged / allowed4 / 5—

All projects in Basingstoke and Deane

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near RG24, 5 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.