Energy Projects Near You

Bramley Frith Solar Farm (49.9 MW)

Bramley Frith Solar Farm is a 49.9 MW solar farm project in Basingstoke and Deane, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 13 February 2023, not yet built; the record was last updated on 30 September 2020. REPD records the planning permission as expiring on 13 February 2026, but the project holds a Contracts for Difference award (AR6), so construction may have started. Check the planning authority's register for the latest position.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

49.9 MWsolar farm
approved, not builtmay be out of datestatus in REPD
30 September 2020record last updated
Basingstoke and Deanecouncil area

REPD records the planning permission as expiring on 13 February 2026, but the project holds a Contracts for Difference award (AR6), so construction may have started.

Planning timeline

DateStage
4 December 2020Application submitted
21 April 2022Refused by the planning authority
4 August 2022Appeal lodged
13 February 2023Planning permission granted
13 February 2023Appeal allowed
13 February 2026Permission expired

Project details

Technology
solar farm
Capacity
49.9 MW
Status (REPD)
approved, not built
Record last updated
30 September 2020
Operator or applicant
Bramley Solar Limited
Planning authority
Basingstoke and Deane
Planning application reference
20/03403/FUL
Appeal reference
22/00035/REF
Site area
85.0 ha
Address (REPD)
Minchens Lane
Council area (by location)
Basingstoke and Deane
Time to decision
114 weeks
Contracts for Difference
AR6
REPD reference
8089

The scheme also includes battery storage, recorded separately in REPD (approved, not built).

Who decides

ApplicationsBasingstoke and DeaneUK
Decided applications (solar, wind, battery)3010,236
Refused8 (27%)19%
Solar refused5 of 2212%
Onshore wind refused1 of 145%
Battery storage refused2 of 716%
Median time from submission to decision26.3 weeks17.0 weeks
Appeals lodged / allowed4 / 5—

Other large projects within 10 km

ProjectTypeMWStatuskm
Withy Place, Bramley Roadbattery storage50approved, not built0.7
Minchens Lane Battery Storage Facilitybattery storage100operational0.8
Ash Lane, Little Londonbattery storage57approved, not built1.2
Frog Lane, Little Londonbattery storage115refused1.6
Beaurepaire Farmsolar farm12refused3.4
Chineham Battery Energy Storage Facilitybattery storage15application withdrawn5.6
Manor Farm, Sherborne Solar Farmsolar farm28application submitted6.2
Bloomfield Hatch Farm Solar Farm & Batterysolar farm25.8approved, not built6.5
Kiln Fields Solar Farmsolar farm17.9under construction7.6

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.3388, -1.0695).