Kiln Fields Solar Farm (17.9 MW)

Kiln Fields Solar Farm is a 17.9 MW solar farm project in Hart, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: under construction since 1 July 2023; the record was last updated on 23 January 2024.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

17.9 MWsolar farm
under constructionstatus in REPD
23 January 2024record last updated
Hartcouncil area

Planning timeline

DateStage
10 November 2021Application submitted
20 December 2021Planning permission granted
1 July 2023Construction started

Project details

Technology
solar farm
Capacity
17.9 MW
Status (REPD)
under construction
Record last updated
23 January 2024
Operator or applicant
Enviromena Asset Management UK Limited
Planning authority
Hart
Planning application reference
21/02749/FUL
Site area
30.0 ha
Address (REPD)
Lying To The N/O Vicarage Lane, Hound Green, Hook
Council area (by location)
Hart
Time to decision
6 weeks
Contracts for Difference
AR6
REPD reference
9941

Who decides

ApplicationsHartUK
Decided applications (solar, wind, battery)1810,236
Refused5 (28%)19%
Solar refused3 of 1012%
Battery storage refused2 of 816%
Median time from submission to decision34.8 weeks17.0 weeks
Appeals lodged / allowed3 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Bunkers Hill Farm Solar farm & Battery stationssolar farm49.9under construction3.2
Holt Lane Solar Parksolar farm22application submitted4.6
Trimmers Solar Farmsolar farm10refused on appeal5.7
Solar Array at Spencers Wood Solar Farm Land north of Sheepbridge Court Farm Basingstoke Road Swallowfieldsolar farm28approved, not built6.1
Sheepbridge Court Farmsolar farm5operational6.9
Taplins Farm solar parksolar farm5.9operational7.0
Aborfield Solar Parksolar farm14under construction7.1
Minchens Lane Battery Storage Facilitybattery storage100operational7.3
Bramley Frith Solar Farmsolar farm49.9approved, not built7.6

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.3277, -0.9619).