Energy Projects Near You

Sheepbridge Court Farm (5 MW solar farm)

Sheepbridge Court Farm is a 5 MW solar farm project in Wokingham, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 20 December 2015; the record was last updated on 4 September 2018.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWsolar farm
operationalstatus in REPD
4 September 2018record last updated
Wokinghamcouncil area

Planning timeline

DateStage
5 August 2014Application submitted
12 December 2014Planning permission granted
20 October 2015Construction started
20 December 2015Operational

Project details

Technology
solar farm
Capacity
5 MW
Status (REPD)
operational
Record last updated
4 September 2018
Operator or applicant
Foresight
Planning authority
Wokingham
Planning application reference
F/2014/1495
Site area
14.1 ha
Address (REPD)
Land at Sheepbridge Court Farm Basingstoke Road Swallowfield Reading
Council area (by location)
Wokingham
Time to decision
18 weeks
REPD reference
2244

Who decides

ApplicationsWokinghamUK
Decided applications (solar, wind, battery)1510,236
Refused1 (7%)19%
Solar refused0 of 1212%
Onshore wind refused1 of 245%
Battery storage refused0 of 116%
Median time from submission to decision12.9 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Solar Array at Spencers Wood Solar Farm Land north of Sheepbridge Court Farm Basingstoke Road Swallowfieldsolar farm28approved, not built0.8
Aborfield Solar Parksolar farm14under construction2.8
Bloomfield Hatch Farm Solar Farm & Batterysolar farm25.8approved, not built3.9
Rushy Mead (University of Reading)wind farm12refused4.1
Pingewood Road Southsolar farm15.8operational4.8
Barkham Farms Solar Farmsolar farm33approved, not built6.2
Motorway Service Area, Burghfield Solar Farmsolar farm5approved, not built6.5
Burghfield Road, Southcotebattery storage7.4application withdrawn6.6
Kiln Fields Solar Farmsolar farm17.9under construction6.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.3895, -0.961).