Aborfield Solar Park (14 MW)

Aborfield Solar Park is a 14 MW solar farm project in Wokingham, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: under construction since 1 July 2021; the record was last updated on 7 April 2021.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

14 MWsolar farm
under constructionstatus in REPD
7 April 2021record last updated
Wokinghamcouncil area

Planning timeline

DateStage
23 March 2020Application submitted
12 March 2021Planning permission granted
1 July 2021Construction started

Project details

Technology
solar farm
Capacity
14 MW
Status (REPD)
under construction
Record last updated
7 April 2021
Operator or applicant
Wessex Solar Energy
Planning authority
Wokingham
Planning application reference
200711
Site area
19.7 ha
Address (REPD)
Bartletts Farm, Swallowfield Road, Arborfield, Reading
Council area (by location)
Wokingham
Time to decision
51 weeks
REPD reference
5371

Who decides

ApplicationsWokinghamUK
Decided applications (solar, wind, battery)1510,236
Refused1 (7%)19%
Solar refused0 of 1212%
Onshore wind refused1 of 245%
Battery storage refused0 of 116%
Median time from submission to decision12.9 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Sheepbridge Court Farmsolar farm5operational2.8
Solar Array at Spencers Wood Solar Farm Land north of Sheepbridge Court Farm Basingstoke Road Swallowfieldsolar farm28approved, not built3.1
Rushy Mead (University of Reading)wind farm12refused3.4
Barkham Farms Solar Farmsolar farm33approved, not built3.5
Bloomfield Hatch Farm Solar Farm & Batterysolar farm25.8approved, not built6.7
Kiln Fields Solar Farmsolar farm17.9under construction7.1
Pingewood Road Southsolar farm15.8operational7.3
Burghfield Road, Southcotebattery storage7.4application withdrawn8.8
Motorway Service Area, Burghfield Solar Farmsolar farm5approved, not built9.1

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.3859, -0.9214).