Energy Projects Near You

Burghfield Road, Southcote (7.4 MW battery storage)

Burghfield Road, Southcote is a 7.4 MW battery storage project in Reading, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: application withdrawn on 19 June 2024; the record was last updated on 8 July 2024.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

7.4 MWbattery storage
application withdrawnstatus in REPD
8 July 2024record last updated
Readingcouncil area

Planning timeline

DateStage
27 September 2023Application submitted
19 June 2024Application withdrawn

Project details

Technology
battery storage (stand-alone storage)
Capacity
7.4 MW
Status (REPD)
application withdrawn
Record last updated
8 July 2024
Operator or applicant
Renepower Energy Limited
Planning authority
Reading
Planning application reference
231000
Address (REPD)
W/O Burghfield Road, Southcote, Reading
Council area (by location)
Reading
Name in REPD
Burghfield Road, Southcote - Battery Storage Facility
REPD reference
15909

Who decides

ApplicationsReadingUK
Decided applications (solar, wind, battery)1010,236
Refused0 (0%)19%
Solar refused0 of 1012%
Median time from submission to decision8.0 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Motorway Service Area, Burghfield Solar Farmsolar farm5approved, not built1.5
Pingewood Road Southsolar farm15.8operational2.1
Sulhamstead Solar Field - Stud Farmsolar farm5approved, not built4.3
Bloomfield Hatch Farm Solar Farm & Batterysolar farm25.8approved, not built5.5
Sheepbridge Court Farmsolar farm5operational6.6
Solar Array at Spencers Wood Solar Farm Land north of Sheepbridge Court Farm Basingstoke Road Swallowfieldsolar farm28approved, not built7.1
Rushy Mead (University of Reading)wind farm12refused7.2
Aborfield Solar Parksolar farm14under construction8.8
Bath Road, Grange Lanesolar farm12approved, not built9.5

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.4363, -1.0199).