Energy Projects Near You

Sulhamstead Solar Field - Stud Farm (5 MW)

Sulhamstead Solar Field - Stud Farm is a 5 MW solar farm project in West Berkshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 12 April 2017, not yet built; the record was last updated on 27 August 2019. REPD also records that the planning permission expired on 1 May 2021, so the project may not go ahead in this form. Check the planning authority's register for the latest position.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWsolar farm
approved, not builtmay be out of datestatus in REPD
27 August 2019record last updated
West Berkshirecouncil area

REPD also records that the planning permission expired on 1 May 2021, so the project may not go ahead in this form.

Planning timeline

DateStage
18 August 2015Application submitted
29 March 2016Refused by the planning authority
1 August 2016Appeal lodged
12 April 2017Planning permission granted
12 April 2017Appeal allowed
1 May 2021Permission expired

Project details

Technology
solar farm
Capacity
5 MW
Status (REPD)
approved, not built
Record last updated
27 August 2019
Operator or applicant
Mulbrick Clean Energy
Planning authority
West Berkshire
Planning application reference
15/02148/COMIND
Appeal reference
APP/W0340/W/16/3154590
Address (REPD)
Land North and S/O Stud Farm, Sulhamstead, Reading
Council area (by location)
West Berkshire
Time to decision
86 weeks
REPD reference
5574

Earlier applications for this site

ApplicationMWSubmittedOutcome
Stud Farm 15/01649/COMIND56 July 2015refused 13 August 2015

Who decides

ApplicationsWest BerkshireUK
Decided applications (solar, wind, battery)3310,236
Refused7 (21%)19%
Solar refused4 of 2512%
Onshore wind refused3 of 345%
Battery storage refused0 of 516%
Median time from submission to decision13.4 weeks17.0 weeks
Appeals lodged / allowed2 / 2—

Other large projects within 10 km

ProjectTypeMWStatuskm
Motorway Service Area, Burghfield Solar Farmsolar farm5approved, not built2.8
Pingewood Road Southsolar farm15.8operational3.5
Bloomfield Hatch Farm Solar Farm & Batterysolar farm25.8approved, not built3.8
Burghfield Road, Southcotebattery storage7.4application withdrawn4.3
Bath Road, Grange Lanesolar farm12approved, not built6.4
Withy Place, Bramley Roadbattery storage50approved, not built7.0
Solar Array at Spencers Wood Solar Farm Land north of Sheepbridge Court Farm Basingstoke Road Swallowfieldsolar farm28approved, not built7.2
Sheepbridge Court Farmsolar farm5operational7.3
Bramley Frith Solar Farmsolar farm49.9approved, not built7.6

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.4075, -1.0619).