Solar, wind and battery projects near Tadley (RG26)
39 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of RG26 (Basingstoke and Deane): 3 are waiting for a planning decision, 25 approved but not yet running, 7 operational. The largest live scheme is Ash Lane, Little London (57 MW battery storage, approved on 9 February 2023, not yet built), 2.9 km away. Source: Renewable Energy Planning Database, July 2026 extract.
Projects within 10 km of RG26
Projects of 1 MW and more (22)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Berry Court Farmsolar farm | solar farm | 4.2 | operationalupdated Nov 2018 | Aug 2014 | granted Apr 2015 | Nov 2018 | Basingstoke and Deane | 1.8 |
| Berry Court Solar Farmbattery storage | battery storage | 1 | operationalupdated Mar 2019 | Jun 2016 | — | Mar 2019 | Basingstoke and Deane | 2.1 |
| Frog Lane, Little Londonbattery storage | battery storage | 115 | refusedupdated Jun 2026 | Apr 2025 | refused May 2026 | Jun 2026 | Basingstoke and Deane | 2.7 |
| Ash Lane, Little Londonbattery storage | battery storage | 57 | approved, not builtupdated Apr 2022 | Jun 2022 | granted Feb 2023 | Apr 2022 | Basingstoke and Deane | 2.9 |
| Hill End Farmsolar farm | solar farm | 2.8 | operationalupdated Aug 2014 | Jul 2013 | granted Dec 2013 | Aug 2014 | Basingstoke and Deane | 3.4 |
| Beaurepaire Farmsolar farm | solar farm | 12 | refusedupdated Sep 2015 | Jun 2013 | refused Jan 2014 | Sep 2015 | Basingstoke and Deane | 3.6 |
| Withy Place, Bramley Roadbattery storage | battery storage | 50 | approved, not builtupdated Jul 2025 | Sep 2024 | granted Jul 2025 | Jul 2025 | Basingstoke and Deane | 4.1 |
| Bramley Frith Solar Farmsolar farm | solar farm | 49.9 | approved, not built may be out of dateupdated Sep 2020 | Dec 2020 | granted Feb 2023 | Sep 2020 | Basingstoke and Deane | 4.2 |
| Minchens Lane Battery Storage Facilitybattery storage | battery storage | 100 | operationalupdated Mar 2026 | Jan 2021 | granted Oct 2021 | Mar 2026 | Basingstoke and Deane | 4.4 |
| Manor Farm, Sherborne Solar Farmsolar farm | solar farm | 28 | application submittedupdated Aug 2025 | Jul 2025 | — | Aug 2025 | Basingstoke and Deane | 4.7 |
| Exolum, Silver Lanesolar farm | solar farm | 1.5 | approved, not builtupdated Jun 2026 | Oct 2025 | granted Jun 2026 | Jun 2026 | West Berkshire | 5.4 |
| Land South of Shothanger Workssolar farm | solar farm | 3.5 | refusedupdated Dec 2015 | Jun 2015 | refused Nov 2015 | Dec 2015 | Basingstoke and Deane | 6.1 |
| Gravel Works, Wasing Estatesolar farm | solar farm | 5 | operationalupdated May 2017 | Mar 2015 | granted Jun 2016 | May 2017 | West Berkshire | 6.3 |
| Chineham Battery Energy Storage Facilitybattery storage | battery storage | 15 | application withdrawnupdated Nov 2018 | Jul 2016 | — | Nov 2018 | Basingstoke and Deane | 6.7 |
| Hook Lane, Malshangersolar farm | solar farm | 30 | approved, not builtupdated May 2026 | Dec 2023 | granted Feb 2026 | May 2026 | Basingstoke and Deane | 7.6 |
| Limberlost Farmsolar farm | solar farm | 1.5 | operationalupdated Feb 2014 | Sep 2012 | granted Dec 2012 | Feb 2014 | West Berkshire | 8.5 |
| Bath Road, Grange Lanesolar farm | solar farm | 12 | approved, not builtupdated Jul 2025 | Oct 2024 | granted Mar 2025 | Jul 2025 | West Berkshire | 8.6 |
| Sulhamstead Solar Field - Stud Farmsolar farm | solar farm | 5 | approved, not built may be out of dateupdated Aug 2019 | Aug 2015 | granted Apr 2017 | Aug 2019 | West Berkshire | 8.9 |
| Basing Roadbattery storage | battery storage | 20 | application submitted may be out of dateupdated Feb 2023 | Jul 2021 | — | Feb 2023 | Basingstoke and Deane | 9.2 |
| Strattons Farm, Newbury Road Solar PV Farmsolar farm | solar farm | 23 | application submitted may be out of dateupdated May 2024 | Apr 2024 | — | May 2024 | Basingstoke and Deane | 9.3 |
| Bloomfield Hatch Farm Solar Farm & Batterysolar farm | solar farm | 25.8 | approved, not built may be out of dateupdated Jun 2025 | May 2022 | granted Sep 2022 | Jun 2025 | West Berkshire | 9.4 |
| Harrods Distribution Centre, Mill Lanerooftop solar | rooftop solar | 1.6 | approved, not built may be out of dateupdated Mar 2023 | Dec 2022 | granted Feb 2023 | Mar 2023 | West Berkshire | 9.4 |
Smaller schemes under 1 MW, mostly rooftop solar (17)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Sainsburys, Mulfords Hillrooftop solar | rooftop solar | 0.4 | approved, not builtupdated Nov 2025 | Aug 2025 | granted Oct 2025 | Nov 2025 | Basingstoke and Deane | 1.9 |
| Ash Lane, Little Londonbattery storage | battery storage | — | approved, not builtupdated May 2025 | Jan 2024 | granted Apr 2025 | May 2025 | Basingstoke and Deane | 3.3 |
| Bramley Frith Solar Farmbattery storage | battery storage | — | approved, not built may be out of dateupdated Feb 2021 | Dec 2020 | granted Feb 2023 | Feb 2021 | Basingstoke and Deane | 4.2 |
| Brickledons Farm, Clappers Farm Roadbattery storage | battery storage | — | approved, not builtupdated Mar 2025 | Nov 2024 | granted Mar 2025 | Mar 2025 | Basingstoke and Deane | 5.2 |
| Lime Tree Way, Crockford Lanesolar farm | solar farm | — | approved, not builtupdated Jan 2026 | Jun 2025 | granted Dec 2025 | Jan 2026 | Basingstoke and Deane | 6.5 |
| Pinewood, Crockford Lanesolar farm | solar farm | 0.2 | approved, not builtupdated Feb 2024 | Dec 2023 | granted Feb 2024 | Feb 2024 | Basingstoke and Deane | 6.8 |
| Padworth Iwmf, Padworth Lanerooftop solar | rooftop solar | 0.9 | approved, not builtupdated Jun 2026 | Apr 2026 | granted May 2026 | Jun 2026 | West Berkshire | 6.9 |
| Inchcape Estates, Edison Roadrooftop solar | rooftop solar | 0.1 | approved, not builtupdated Jul 2023 | Jun 2023 | granted Jul 2023 | Jul 2023 | Basingstoke and Deane | 7.3 |
| Gemini Centre, Hamilton Closerooftop solar | rooftop solar | 0.3 | approved, not builtupdated May 2023 | Mar 2023 | granted May 2023 | May 2023 | Basingstoke and Deane | 7.5 |
| Worting Roadrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Nov 2021 | Sep 2021 | granted Nov 2021 | Nov 2021 | Basingstoke and Deane | 8.2 |
| Hollywood Bowl, Basingstoke Leisure Park Solar Panel Photovoltaicsrooftop solar | rooftop solar | 0.2 | approved, not builtupdated May 2022 | May 2022 | granted Jul 2022 | May 2022 | Basingstoke and Deane | 8.4 |
| Limberlost Solar Farmbattery storage | battery storage | 0.3 | operationalupdated Nov 2016 | — | — | Nov 2016 | West Berkshire | 8.5 |
| Bath Road, Grange Lanebattery storage | battery storage | — | approved, not builtupdated Jul 2025 | Oct 2024 | granted Mar 2025 | Jul 2025 | West Berkshire | 8.6 |
| Worting Roadrooftop solar | rooftop solar | 0.5 | approved, not builtupdated Dec 2021 | Nov 2021 | granted Feb 2022 | Dec 2021 | Basingstoke and Deane | 8.7 |
| Hillfields, Burghfield Commonrooftop solar | rooftop solar | 0.4 | approved, not builtupdated Nov 2023 | Jun 2023 | granted Nov 2023 | Nov 2023 | West Berkshire | 9.3 |
| The Costello Schoolrooftop solar | rooftop solar | — | approved, not builtupdated Nov 2025 | Jul 2025 | granted Oct 2025 | Nov 2025 | Basingstoke and Deane | 9.3 |
| Bloomfield Hatch Farm Solar Farm & Batterybattery storage | battery storage | — | approved, not built may be out of dateupdated Jun 2025 | May 2022 | granted Sep 2022 | Jun 2025 | West Berkshire | 9.4 |
Distance from the average position of the RG26 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.
By type
| Type | All | Pending | Approved | Operational | Refused | MW in pipeline |
|---|---|---|---|---|---|---|
| Solar farm | 16 | 2 | 8 | 4 | 2 | 175 |
| Rooftop solar | 10 | 0 | 10 | 0 | 0 | 4.7 |
| Battery storage | 13 | 1 | 7 | 3 | 1 | 127 |
MW in pipeline: pending, approved and under-construction capacity.
How Basingstoke and Deane decides solar, wind and battery applications
| Applications | Basingstoke and Deane | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 30 | 10,236 |
| Refused | 8 (27%) | 19% |
| Solar refused | 5 of 22 | 12% |
| Onshore wind refused | 1 of 1 | 45% |
| Battery storage refused | 2 of 7 | 16% |
| Median time from submission to decision | 26.3 weeks | 17.0 weeks |
| Appeals lodged / allowed | 4 / 5 | — |
All projects in Basingstoke and Deane
Is the status up to date?
32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near RG26, 8 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.