Gravel Works, Wasing Estate (5 MW solar farm)

Gravel Works, Wasing Estate is a 5 MW solar farm project in West Berkshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 1 March 2017; the record was last updated on 3 May 2017.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWsolar farm
operationalstatus in REPD
3 May 2017record last updated
West Berkshirecouncil area

Planning timeline

DateStage
20 March 2015Application submitted
18 September 2015Refused by the planning authority
4 February 2016Appeal lodged
9 June 2016Planning permission granted
9 June 2016Appeal allowed
1 February 2017Construction started
1 March 2017Operational

Project details

Technology
solar farm
Capacity
5 MW
Status (REPD)
operational
Record last updated
3 May 2017
Operator or applicant
NESF (formerly INRG Solar)
Planning authority
West Berkshire
Planning application reference
15/00557/COMIND
Appeal reference
APP/W0340/W/16/3141813
Site area
11.4 ha
Address (REPD)
Land West Of Gravel Works, Station Road, Woolhampton, Reading, Berkshire
Council area (by location)
West Berkshire
Time to decision
64 weeks
REPD reference
5143

Who decides

ApplicationsWest BerkshireUK
Decided applications (solar, wind, battery)3310,236
Refused7 (21%)19%
Solar refused4 of 2512%
Onshore wind refused3 of 345%
Battery storage refused0 of 516%
Median time from submission to decision13.4 weeks17.0 weeks
Appeals lodged / allowed2 / 2—

Other large projects within 10 km

ProjectTypeMWStatuskm
Bath Road, Grange Lanesolar farm12approved, not built4.9
Strattons Farm, Newbury Road Solar PV Farmsolar farm23application submitted6.2
Frog Lane, Little Londonbattery storage115refused8.6
Ash Lane, Little Londonbattery storage57approved, not built8.6
Withy Place, Bramley Roadbattery storage50approved, not built9.3
Sulhamstead Solar Field - Stud Farmsolar farm5approved, not built9.6
Bramley Frith Solar Farmsolar farm49.9approved, not built9.7
Beaurepaire Farmsolar farm12refused9.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.3797, -1.1932).