Beaurepaire Farm (12 MW solar farm)
Beaurepaire Farm is a 12 MW solar farm project in Basingstoke and Deane, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on 24 January 2014; the record was last updated on 30 September 2015.
12 MWsolar farm
refusedstatus in REPD
30 September 2015record last updated
Basingstoke and Deanecouncil area
Planning timeline
| Date | Stage |
|---|---|
| 10 June 2013 | Application submitted |
| 24 January 2014 | Refused by the planning authority |
Project details
- Technology
- solar farm
- Capacity
- 12 MW
- Status (REPD)
- refused
- Record last updated
- 30 September 2015
- Operator or applicant
- KS SPV33 Ltd
- Planning authority
- Basingstoke and Deane
- Planning application reference
- 13/00751/FUL
- Address (REPD)
- Land at Beaurepaire Farm New Road Bramley Tadley Hampshire RG26 5ED
- Council area (by location)
- Basingstoke and Deane
- Time to decision
- 33 weeks
- REPD reference
- 1683
Who decides
| Applications | Basingstoke and Deane | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 30 | 10,236 |
| Refused | 8 (27%) | 19% |
| Solar refused | 5 of 22 | 12% |
| Onshore wind refused | 1 of 1 | 45% |
| Battery storage refused | 2 of 7 | 16% |
| Median time from submission to decision | 26.3 weeks | 17.0 weeks |
| Appeals lodged / allowed | 4 / 5 | — |
Other large projects within 10 km
| Project | Type | MW | Status | km |
|---|---|---|---|---|
| Frog Lane, Little London | battery storage | 115 | refused | 2.4 |
| Manor Farm, Sherborne Solar Farm | solar farm | 28 | application submitted | 2.8 |
| Ash Lane, Little London | battery storage | 57 | approved, not built | 2.9 |
| Minchens Lane Battery Storage Facility | battery storage | 100 | operational | 2.9 |
| Chineham Battery Energy Storage Facility | battery storage | 15 | application withdrawn | 3.1 |
| Bramley Frith Solar Farm | solar farm | 49.9 | approved, not built | 3.4 |
| Withy Place, Bramley Road | battery storage | 50 | approved, not built | 3.9 |
| Basing Road | battery storage | 20 | application submitted | 5.6 |
| Hook Lane, Malshanger | solar farm | 30 | approved, not built | 6.8 |
Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.3141, -1.0982).