Minchens Lane Battery Storage Facility (100 MW)

Minchens Lane Battery Storage Facility is a 100 MW battery storage project in Basingstoke and Deane, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 1 February 2025; the record was last updated on 9 March 2026.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

100 MWbattery storage
operationalstatus in REPD
9 March 2026record last updated
Basingstoke and Deanecouncil area

Planning timeline

DateStage
29 January 2021Application submitted
8 October 2021Planning permission granted
22 December 2021Appeal lodged
26 January 2023Appeal allowed
1 February 2025Operational

Project details

Technology
battery storage (stand-alone storage)
Capacity
100 MW
Status (REPD)
operational
Record last updated
9 March 2026
Operator or applicant
Penso Power (BW ESS)
Planning authority
Basingstoke and Deane
Planning application reference
21/00349/FUL
Address (REPD)
OS Ref 464762 159811 Minchens Lane Bramley
Council area (by location)
Basingstoke and Deane
Time to decision
36 weeks
REPD reference
8434

Who decides

ApplicationsBasingstoke and DeaneUK
Decided applications (solar, wind, battery)3010,236
Refused8 (27%)19%
Solar refused5 of 2212%
Onshore wind refused1 of 145%
Battery storage refused2 of 716%
Median time from submission to decision26.3 weeks17.0 weeks
Appeals lodged / allowed4 / 5—

Other large projects within 10 km

ProjectTypeMWStatuskm
Bramley Frith Solar Farmsolar farm49.9approved, not built0.8
Withy Place, Bramley Roadbattery storage50approved, not built1.5
Ash Lane, Little Londonbattery storage57approved, not built1.6
Frog Lane, Little Londonbattery storage115refused1.8
Beaurepaire Farmsolar farm12refused2.9
Chineham Battery Energy Storage Facilitybattery storage15application withdrawn4.8
Manor Farm, Sherborne Solar Farmsolar farm28application submitted5.7
Basing Roadbattery storage20application submitted7.0
Bloomfield Hatch Farm Solar Farm & Batterysolar farm25.8approved, not built7.1