Solar, wind and battery projects near Reading (RG7)
45 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of RG7 (West Berkshire): 1 is waiting for a planning decision, 31 approved but not yet running, 9 operational. The largest live scheme is Ash Lane, Little London (57 MW battery storage, approved on 9 February 2023, not yet built), 6.6 km away. Source: Renewable Energy Planning Database, July 2026 extract.
Projects within 10 km of RG7
Projects of 1 MW and more (22)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Sulhamstead Solar Field - Stud Farmsolar farm | solar farm | 5 | approved, not built may be out of dateupdated Aug 2019 | Aug 2015 | granted Apr 2017 | Aug 2019 | West Berkshire | 1.5 |
| Exolum, Silver Lanesolar farm | solar farm | 1.5 | approved, not builtupdated Jun 2026 | Oct 2025 | granted Jun 2026 | Jun 2026 | West Berkshire | 2.2 |
| Pierces Farmsolar farm | solar farm | 1.7 | operationalupdated Jul 2018 | Dec 2013 | granted Mar 2014 | Jul 2018 | West Berkshire | 3.8 |
| Motorway Service Area, Burghfield Solar Farmsolar farm | solar farm | 5 | approved, not builtupdated Oct 2025 | Mar 2025 | granted Sep 2025 | Oct 2025 | West Berkshire | 4.3 |
| Bloomfield Hatch Farm Solar Farm & Batterysolar farm | solar farm | 25.8 | approved, not built may be out of dateupdated Jun 2025 | May 2022 | granted Sep 2022 | Jun 2025 | West Berkshire | 4.3 |
| Pingewood Road Southsolar farm | solar farm | 15.8 | operationalupdated Nov 2015 | Jul 2014 | granted Oct 2014 | Nov 2015 | West Berkshire | 4.9 |
| Bath Road, Grange Lanesolar farm | solar farm | 12 | approved, not builtupdated Jul 2025 | Oct 2024 | granted Mar 2025 | Jul 2025 | West Berkshire | 5.6 |
| Burghfield Road, Southcotebattery storage | battery storage | 7.4 | application withdrawnupdated Jul 2024 | Sep 2023 | — | Jul 2024 | Reading | 5.8 |
| Withy Place, Bramley Roadbattery storage | battery storage | 50 | approved, not builtupdated Jul 2025 | Sep 2024 | granted Jul 2025 | Jul 2025 | Basingstoke and Deane | 5.9 |
| Ash Lane, Little Londonbattery storage | battery storage | 57 | approved, not builtupdated Apr 2022 | Jun 2022 | granted Feb 2023 | Apr 2022 | Basingstoke and Deane | 6.6 |
| Bramley Frith Solar Farmsolar farm | solar farm | 49.9 | approved, not built may be out of dateupdated Sep 2020 | Dec 2020 | granted Feb 2023 | Sep 2020 | Basingstoke and Deane | 6.6 |
| Green Parkwind turbine | wind turbine | 2 | operationalupdated May 2009 | Mar 2004 | granted Jul 2004 | May 2009 | Wokingham | 6.8 |
| Frog Lane, Little Londonbattery storage | battery storage | 115 | refusedupdated Jun 2026 | Apr 2025 | refused May 2026 | Jun 2026 | Basingstoke and Deane | 7.0 |
| Minchens Lane Battery Storage Facilitybattery storage | battery storage | 100 | operationalupdated Mar 2026 | Jan 2021 | granted Oct 2021 | Mar 2026 | Basingstoke and Deane | 7.4 |
| Solar Array at Spencers Wood Solar Farm Land north of Sheepbridge Court Farm Basingstoke Road Swallowfieldsolar farm | solar farm | 28 | approved, not builtupdated Feb 2026 | Nov 2023 | granted Mar 2025 | Feb 2026 | Wokingham | 7.9 |
| Sheepbridge Court Farmsolar farm | solar farm | 5 | operationalupdated Sep 2018 | Aug 2014 | granted Dec 2014 | Sep 2018 | Wokingham | 8.1 |
| Berry Court Farmsolar farm | solar farm | 4.2 | operationalupdated Nov 2018 | Aug 2014 | granted Apr 2015 | Nov 2018 | Basingstoke and Deane | 8.2 |
| Gravel Works, Wasing Estatesolar farm | solar farm | 5 | operationalupdated May 2017 | Mar 2015 | granted Jun 2016 | May 2017 | West Berkshire | 8.3 |
| Berry Court Solar Farmbattery storage | battery storage | 1 | operationalupdated Mar 2019 | Jun 2016 | — | Mar 2019 | Basingstoke and Deane | 8.3 |
| Mazelands Farmsolar farm | solar farm | 2.8 | refusedupdated May 2016 | Sep 2015 | refused Apr 2016 | May 2016 | West Berkshire | 9.4 |
| Beaurepaire Farmsolar farm | solar farm | 12 | refusedupdated Sep 2015 | Jun 2013 | refused Jan 2014 | Sep 2015 | Basingstoke and Deane | 9.4 |
| Hill End Farmsolar farm | solar farm | 2.8 | operationalupdated Aug 2014 | Jul 2013 | granted Dec 2013 | Aug 2014 | Basingstoke and Deane | 9.9 |
Smaller schemes under 1 MW, mostly rooftop solar (23)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Hillfields, Burghfield Commonrooftop solar | rooftop solar | 0.4 | approved, not builtupdated Nov 2023 | Jun 2023 | granted Nov 2023 | Nov 2023 | West Berkshire | 2.3 |
| Padworth Iwmf, Padworth Lanerooftop solar | rooftop solar | 0.9 | approved, not builtupdated Jun 2026 | Apr 2026 | granted May 2026 | Jun 2026 | West Berkshire | 3.7 |
| MOTO Reading Services - Tesla Megapack & EV Chargingbattery storage | battery storage | — | approved, not builtupdated Mar 2024 | Jan 2024 | granted Mar 2024 | Mar 2024 | West Berkshire | 4.2 |
| Arlington Business Park, Theale - Roof Mounted Solar panel PVrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Dec 2024 | Oct 2024 | granted Dec 2024 | Dec 2024 | West Berkshire | 4.3 |
| Motorway Service Area, Burghfield Solar Farmbattery storage | battery storage | — | approved, not builtupdated Oct 2025 | Mar 2025 | granted Sep 2025 | Oct 2025 | West Berkshire | 4.3 |
| Bloomfield Hatch Farm Solar Farm & Batterybattery storage | battery storage | — | approved, not built may be out of dateupdated Jun 2025 | May 2022 | granted Sep 2022 | Jun 2025 | West Berkshire | 4.3 |
| Brickledons Farm, Clappers Farm Roadbattery storage | battery storage | — | approved, not builtupdated Mar 2025 | Nov 2024 | granted Mar 2025 | Mar 2025 | Basingstoke and Deane | 5.3 |
| Bath Road, Grange Lanebattery storage | battery storage | — | approved, not builtupdated Jul 2025 | Oct 2024 | granted Mar 2025 | Jul 2025 | West Berkshire | 5.6 |
| Ash Lane, Little Londonbattery storage | battery storage | — | approved, not builtupdated May 2025 | Jan 2024 | granted Apr 2025 | May 2025 | Basingstoke and Deane | 6.5 |
| Sainsburys, Mulfords Hillrooftop solar | rooftop solar | 0.4 | approved, not builtupdated Nov 2025 | Aug 2025 | granted Oct 2025 | Nov 2025 | Basingstoke and Deane | 6.5 |
| Bramley Frith Solar Farmbattery storage | battery storage | — | approved, not built may be out of dateupdated Feb 2021 | Dec 2020 | granted Feb 2023 | Feb 2021 | Basingstoke and Deane | 6.6 |
| Voco Reading Hotel, Shooters Wayrooftop solar | rooftop solar | 0.4 | approved, not builtupdated Mar 2024 | Jan 2024 | granted Mar 2024 | Mar 2024 | Reading | 7.1 |
| Mereoak Park And Ride, Mereoak Lane Solar Canopiessolar farm | solar farm | — | approved, not builtupdated Dec 2025 | Sep 2025 | granted Nov 2025 | Dec 2025 | Wokingham | 7.2 |
| Reading International Business Parkrooftop solar | rooftop solar | 0.3 | approved, not built may be out of dateupdated Nov 2021 | Oct 2021 | granted Dec 2021 | Nov 2021 | Reading | 7.3 |
| Reading International Business Park - Car Port & Solar Panelssolar farm | solar farm | — | approved, not builtupdated Jan 2024 | Sep 2023 | granted Jan 2024 | Jan 2024 | Reading | 7.3 |
| Reading International Business Park, Relief Roadrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Jun 2023 | Mar 2023 | granted May 2023 | Jun 2023 | Reading | 7.3 |
| Relief Roadrooftop solar | rooftop solar | 0.6 | approved, not built may be out of dateupdated Feb 2022 | Nov 2021 | granted Feb 2022 | Feb 2022 | Reading | 7.3 |
| Starline Holdings Technology, Island Roadrooftop solar | rooftop solar | 0.5 | approved, not builtupdated Apr 2024 | Jan 2024 | granted Mar 2024 | Apr 2024 | Reading | 7.5 |
| Arena Business Park, Acre Road- Photovoltaics Solar Panelsrooftop solar | rooftop solar | 0.3 | approved, not builtupdated May 2023 | Feb 2023 | granted Apr 2023 | May 2023 | Reading | 7.5 |
| Solar Array at Spencers Wood Solar Farm Land north of Sheepbridge Court Farm Basingstoke Road Swallowfieldbattery storage | battery storage | — | approved, not builtupdated Feb 2026 | Nov 2023 | granted Mar 2025 | Feb 2026 | Wokingham | 7.9 |
| Portman Road Tesco (Reading West)rooftop solar | rooftop solar | 0.2 | approved, not built may be out of dateupdated Apr 2021 | Feb 2020 | granted May 2020 | Apr 2021 | Reading | 8.7 |
| Big Yellow Self Storage Building, Rose Kiln Lanerooftop solar | rooftop solar | 0.2 | application submitted may be out of dateupdated Jul 2025 | Jul 2024 | — | Jul 2025 | Reading | 8.7 |
| The Globe, Portman Roadrooftop solar | rooftop solar | 0.2 | approved, not built may be out of dateupdated Apr 2024 | Feb 2024 | granted Mar 2024 | Apr 2024 | Reading | 8.9 |
Distance from the average position of the RG7 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.
By type
| Type | All | Pending | Approved | Operational | Refused | MW in pipeline |
|---|---|---|---|---|---|---|
| Solar farm | 17 | 0 | 9 | 6 | 2 | 127 |
| Rooftop solar | 13 | 1 | 12 | 0 | 0 | 4.8 |
| Wind turbine | 1 | 0 | 0 | 1 | 0 | 0 |
| Battery storage | 14 | 0 | 10 | 2 | 1 | 107 |
MW in pipeline: pending, approved and under-construction capacity.
How West Berkshire decides solar, wind and battery applications
| Applications | West Berkshire | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 33 | 10,236 |
| Refused | 7 (21%) | 19% |
| Solar refused | 4 of 25 | 12% |
| Onshore wind refused | 3 of 3 | 45% |
| Battery storage refused | 0 of 5 | 16% |
| Median time from submission to decision | 13.4 weeks | 17.0 weeks |
| Appeals lodged / allowed | 2 / 2 | — |
All projects in West Berkshire
Is the status up to date?
32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near RG7, 10 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.