Energy Projects Near You

Hook Lane, Malshanger (30 MW solar farm)

Hook Lane, Malshanger is a 30 MW solar farm project in Basingstoke and Deane, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 13 February 2026, not yet built; the record was last updated on 19 May 2026.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

30 MWsolar farm
approved, not builtstatus in REPD
19 May 2026record last updated
Basingstoke and Deanecouncil area

Planning timeline

DateStage
5 December 2023Application submitted
13 February 2026Planning permission granted
13 February 2029Permission due to expire (unless work starts)

Project details

Technology
solar farm
Capacity
30 MW
Status (REPD)
approved, not built
Record last updated
19 May 2026
Operator or applicant
Nextpower SPV 18 Limited
Planning authority
Basingstoke and Deane
Planning application reference
23/03012/FUL
Site area
68.9 ha
Address (REPD)
Malshanger Estate, Hook Lane, Upper Wootton, Tadley,
Council area (by location)
Basingstoke and Deane
Time to decision
114 weeks
REPD reference
7962

Who decides

ApplicationsBasingstoke and DeaneUK
Decided applications (solar, wind, battery)3010,236
Refused8 (27%)19%
Solar refused5 of 2212%
Onshore wind refused1 of 145%
Battery storage refused2 of 716%
Median time from submission to decision26.3 weeks17.0 weeks
Appeals lodged / allowed4 / 5—

Other large projects within 10 km

ProjectTypeMWStatuskm
Manor Farm, Sherborne Solar Farmsolar farm28application submitted3.9
Beaurepaire Farmsolar farm12refused6.8
Chineham Battery Energy Storage Facilitybattery storage15application withdrawn7.0
Basing Roadbattery storage20application submitted8.1
Frog Lane, Little Londonbattery storage115refused8.7
Ash Lane, Little Londonbattery storage57approved, not built9.2
Strattons Farm, Newbury Road Solar PV Farmsolar farm23application submitted9.4
Minchens Lane Battery Storage Facilitybattery storage100operational9.7

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.2785, -1.1773).