Energy Projects Near You

Solar, wind and battery projects near Wokingham (RG41)

31 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of RG41 (Wokingham): 3 are waiting for a planning decision, 25 approved but not yet running, 2 operational. The largest live scheme is Barkham Farms Solar Farm (33 MW solar farm, approved on 21 January 2022, not yet built; REPD status may be out of date), 3.3 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

31projects within 10 km
3awaiting a decision
25approved, not running
2operational

Projects within 10 km of RG41

Projects of 1 MW and more (8)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Barkham Farms Solar Farmsolar farmsolar farm33approved, not built may be out of dateupdated Feb 2021Mar 2021granted Jan 2022Feb 2021Wokingham3.3
Rushy Mead (University of Reading)wind farmwind farm12refusedupdated Oct 2011Oct 2010refused Apr 2011Oct 2011Wokingham4.1
Aborfield Solar Parksolar farmsolar farm14under constructionupdated Apr 2021Mar 2020granted Mar 2021Apr 2021Wokingham5.3
Billingbear Solar Farmsolar farmsolar farm21.5approved, not builtupdated Oct 2024Oct 2022granted Jul 2024Oct 2024Windsor and Maidenhead6.1
Suttons Park Avenue, Suttons Business Parkrooftop solarrooftop solar1.3approved, not builtupdated Aug 2023Jun 2023granted Aug 2023Aug 2023Wokingham7.0
Sheepbridge Court Farmsolar farmsolar farm5operationalupdated Sep 2018Aug 2014granted Dec 2014Sep 2018Wokingham7.5
Solar Array at Spencers Wood Solar Farm Land north of Sheepbridge Court Farm Basingstoke Road Swallowfieldsolar farmsolar farm28approved, not builtupdated Feb 2026Nov 2023granted Mar 2025Feb 2026Wokingham8.1
Green Parkwind turbinewind turbine2operationalupdated May 2009Mar 2004granted Jul 2004May 2009Wokingham8.5
Smaller schemes under 1 MW, mostly rooftop solar (23)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Rectory Roadrooftop solarrooftop solar—approved, not built may be out of dateupdated Apr 2021Jan 2021granted Apr 2021Apr 2021Wokingham2.0
Eskdale Road, Winnershrooftop solarrooftop solar0.2approved, not builtupdated Sep 2022Aug 2022granted Sep 2022Sep 2022Wokingham2.8
Henry Street Garden Centre, Swallowfield Road,rooftop solarrooftop solar0.4approved, not builtupdated Dec 2023Nov 2023granted Nov 2023Dec 2023Wokingham4.7
Woodley Library Solar Planelsrooftop solarrooftop solar—approved, not built may be out of dateupdated May 2021May 2021granted Jun 2021May 2021Wokingham4.9
John Nike Way, Binfieldsolar farmsolar farm0.8application submittedupdated Mar 2026Feb 2026—Mar 2026Bracknell Forest5.1
David Lloyd Leisure, Thames Valley Park Driverooftop solarrooftop solar—approved, not builtupdated Jun 2023May 2023granted Jun 2023Jun 2023Wokingham6.8
Thames Valley Park Drive, Earley - Photovoltaic Solar panelsrooftop solarrooftop solar0.2approved, not builtupdated Apr 2022Apr 2022granted May 2022Apr 2022Wokingham7.1
The Paddock Centre, Joshua Jebb Wayrooftop solarrooftop solar0.2approved, not builtupdated Feb 2025Dec 2024granted Jan 2025Feb 2025Bracknell Forest7.6
Thames Valley University, Kings Roadrooftop solarrooftop solar—application submittedupdated May 2026Jan 2026—May 2026Reading7.6
Edgbarrow School, Grant Roadrooftop solarrooftop solar0.2approved, not builtApr 2026granted Jun 2026—Bracknell Forest7.7
Relief Roadrooftop solarrooftop solar0.6approved, not built may be out of dateupdated Feb 2022Nov 2021granted Feb 2022Feb 2022Reading7.8
Reading International Business Park, Relief Roadrooftop solarrooftop solar0.2approved, not builtupdated Jun 2023Mar 2023granted May 2023Jun 2023Reading7.8
Reading International Business Parkrooftop solarrooftop solar0.3approved, not built may be out of dateupdated Nov 2021Oct 2021granted Dec 2021Nov 2021Reading7.8
Reading International Business Park - Car Port & Solar Panelssolar farmsolar farm—approved, not builtupdated Jan 2024Sep 2023granted Jan 2024Jan 2024Reading7.8
Mereoak Park And Ride, Mereoak Lane Solar Canopiessolar farmsolar farm—approved, not builtupdated Dec 2025Sep 2025granted Nov 2025Dec 2025Wokingham7.9
Broadmoor Hospital, Lower Broadmoor Roadrooftop solarrooftop solar0.4approved, not builtupdated Apr 2026Mar 2025granted Feb 2026Apr 2026Bracknell Forest7.9
Arena Business Park, Acre Road- Photovoltaics Solar Panelsrooftop solarrooftop solar0.3approved, not builtupdated May 2023Feb 2023granted Apr 2023May 2023Reading8.0
Solar Array at Spencers Wood Solar Farm Land north of Sheepbridge Court Farm Basingstoke Road Swallowfieldbattery storagebattery storage—approved, not builtupdated Feb 2026Nov 2023granted Mar 2025Feb 2026Wokingham8.1
Big Yellow Self Storage Building, Rose Kiln Lanerooftop solarrooftop solar0.2application submitted may be out of dateupdated Jul 2025Jul 2024—Jul 2025Reading8.3
Voco Reading Hotel, Shooters Wayrooftop solarrooftop solar0.4approved, not builtupdated Mar 2024Jan 2024granted Mar 2024Mar 2024Reading8.4
David Lloyd Royal Berkshirerooftop solarrooftop solar—approved, not builtupdated Sep 2025Jul 2025granted Sep 2025Sep 2025Bracknell Forest8.7
Starline Holdings Technology, Island Roadrooftop solarrooftop solar0.5approved, not builtupdated Apr 2024Jan 2024granted Mar 2024Apr 2024Reading8.7
St Lukes Residential Care Home, Marshland Squaresolar farmsolar farm0.2approved, not builtupdated Nov 2025May 2025granted Jul 2025Nov 2025Reading10.0

Distance from the average position of the RG41 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm9171097.5
Rooftop solar19217005.3
Wind farm100010
Wind turbine100100
Battery storage101000

MW in pipeline: pending, approved and under-construction capacity.

How Wokingham decides solar, wind and battery applications

ApplicationsWokinghamUK
Decided applications (solar, wind, battery)1510,236
Refused1 (7%)19%
Solar refused0 of 1212%
Onshore wind refused1 of 245%
Battery storage refused0 of 116%
Median time from submission to decision12.9 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

All projects in Wokingham

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near RG41, 6 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.