Bunkers Hill Farm Solar farm & Battery stations (49.9 MW)

Bunkers Hill Farm Solar farm & Battery stations is a 49.9 MW solar farm project in Hart, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: under construction since 15 May 2023; the record was last updated on 11 January 2022.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

49.9 MWsolar farm
under constructionstatus in REPD
11 January 2022record last updated
Hartcouncil area

Planning timeline

DateStage
25 February 2021Application submitted
11 November 2021Planning permission granted
15 May 2023Construction started

Project details

Technology
solar farm
Capacity
49.9 MW
Status (REPD)
under construction
Record last updated
11 January 2022
Operator or applicant
Vantage RE
Planning authority
Hart
Planning application reference
21/00552/FUL
Site area
70.1 ha
Address (REPD)
Bunkers Hill Farm Reading Road Rotherwick Hook
Council area (by location)
Hart
Time to decision
37 weeks
Contracts for Difference
AR4
Name in REPD
Bunkers Hill Farm - Solar farm & Battery stations
REPD reference
8149

The scheme also includes battery storage, recorded separately in REPD (under construction).

Who decides

ApplicationsHartUK
Decided applications (solar, wind, battery)1810,236
Refused5 (28%)19%
Solar refused3 of 1012%
Battery storage refused2 of 816%
Median time from submission to decision34.8 weeks17.0 weeks
Appeals lodged / allowed3 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Holt Lane Solar Parksolar farm22application submitted1.5
Trimmers Solar Farmsolar farm10refused on appeal2.8
Kiln Fields Solar Farmsolar farm17.9under construction3.2
Taplins Farm solar parksolar farm5.9operational5.2
Hungerford Farmsolar farm5operational5.7
Chosley Farm, North Warnborough Solar Farm and Battery storagesolar farm49.9approved, not built5.8
Fleet Substationbattery storage49.9application withdrawn7.5
Coxmoor Wood, Crondall Roadbattery storage57approved, not built7.6
Blue Bell Lodge, Rye Common Lanebattery storage49.5approved, not built7.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.2996, -0.9562).