Energy Projects Near You

Solar, wind and battery projects near Fleet (GU52)

38 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of GU52 (Hart): 4 are waiting for a planning decision, 22 approved but not yet running, 4 operational. The largest live scheme is Penn Croft Farm, Crondall (100 MW battery storage, approved on 30 January 2023, not yet built; REPD status may be out of date), 4.6 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

38projects within 10 km
4awaiting a decision
22approved, not running
4operational

Projects within 10 km of GU52

Projects of 1 MW and more (21)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Coxmoor Wood, Crondall Roadbattery storagebattery storage57approved, not builtupdated May 2024Apr 2023granted Apr 2024May 2024Hart1.9
Crondall Road, Crondall - Fleet Bramley Battery Energy Storagebattery storagebattery storage99.9approved, not builtupdated Sep 2025Jan 2025granted Aug 2025Sep 2025Hart2.3
Blue Bell Lodge, Rye Common Lanebattery storagebattery storage49.5approved, not built may be out of dateupdated Sep 2023Jan 2023granted May 2023Sep 2023Hart2.9
Bowenhurst Farm, Mill Lanebattery storagebattery storage100refusedupdated Apr 2026Jul 2025refused Feb 2026Apr 2026Hart3.0
Fleet Substationbattery storagebattery storage49.9application withdrawnupdated Dec 2019Jun 2019—Dec 2019Hart3.1
Rye Commonbattery storagebattery storage49.5approved, not built may be out of dateupdated Mar 2020Mar 2020granted Sep 2021Mar 2020Hart3.1
Hungerford Farmsolar farmsolar farm5operationalupdated Oct 2016Jul 2015granted Oct 2015Oct 2016Hart3.4
Taplins Farm solar parksolar farmsolar farm5.9operationalupdated Jul 2016May 2014granted Oct 2014Jul 2016Hart4.2
Penn Croft Farm, Crondallbattery storagebattery storage100approved, not built may be out of dateupdated Dec 2021Dec 2021granted Jan 2023Dec 2021Hart4.6
Farnborough Airportrooftop solarrooftop solar1.7operationalupdated Nov 2024Aug 2023granted Oct 2023Nov 2024Rushmoor4.9
Farnborough International Exhibition Centre, Etps Roadrooftop solarrooftop solar1.1under constructionupdated Feb 2024Dec 2023granted Feb 2024Feb 2024Rushmoor5.8
Potbridge Farmsolar farmsolar farm4appeal withdrawnupdated Jul 2016Jul 2015refused Oct 2015Jul 2016Hart6.4
Marsh House Solar Parksolar farmsolar farm5.5operationalupdated Apr 2015Mar 2012granted Dec 2013Apr 2015East Hampshire6.4
Trimmers Solar Farmsolar farmsolar farm10refused on appealupdated May 2016Aug 2015refused Nov 2015May 2016Hart6.4
Fleet Hill Solar Farmsolar farmsolar farm47.5under constructionupdated Jun 2026Jan 2024granted Apr 2025Jun 2026Hart7.9
Holt Lane Solar Parksolar farmsolar farm22application submittedupdated Jun 2025May 2025—Jun 2025Hart7.9
Chosley Farm, North Warnborough Solar Farm and Battery storagesolar farmsolar farm49.9approved, not built may be out of dateupdated Feb 2026Jan 2021granted Nov 2021Feb 2026Hart8.6
Bunkers Hill Farm Solar farm & Battery stationssolar farmsolar farm49.9under constructionupdated Jan 2022Feb 2021granted Nov 2021Jan 2022Hart9.1
Data Centre, Dennison House, Stanhope Roadrooftop solarrooftop solar1.1approved, not builtupdated Jan 2025Nov 2024granted Jan 2025Jan 2025Surrey Heath9.3
Stanhope Roadrooftop solarrooftop solar1.2refusedupdated May 2024Jan 2024refused Mar 2024May 2024Surrey Heath9.4
Stanhope Roadrooftop solarrooftop solar1.2refusedupdated Jul 2024May 2024refused Jul 2024Jul 2024Surrey Heath9.4
Smaller schemes under 1 MW, mostly rooftop solar (17)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Templer Avenue Solar Photovoltaic Panelsolar farmsolar farm0.2approved, not builtupdated Dec 2022Nov 2022granted Dec 2022Dec 2022Rushmoor5.5
Weybourne Roadbattery storagebattery storage0.2refusedupdated Jan 2025Aug 2024refused Nov 2024Jan 2025Waverley5.5
University For The Creative Arts, Falkner Roadrooftop solarrooftop solar0.6approved, not builtupdated Sep 2023Jul 2023granted Sep 2023Sep 2023Waverley5.8
University For The Creative Arts, Falkner Road - ASHP & Battery Storagebattery storagebattery storage—approved, not built may be out of dateupdated May 2024Nov 2023granted Mar 2024May 2024Waverley5.8
Invincible Roadrooftop solarrooftop solar0.1approved, not built may be out of dateupdated Jun 2023May 2023granted Jun 2023Jun 2023Rushmoor5.9
David Lloyd Leisure Club, Wilkinson Wayrooftop solarrooftop solar0.3approved, not builtupdated Sep 2023Jul 2023granted Sep 2023Sep 2023Waverley6.0
Brightwells Roadrooftop solarrooftop solar0.3approved, not built may be out of dateupdated Jul 2022Jul 2022granted Nov 2022Jul 2022Waverley6.0
Kinetrol Manufacturing,Farnham Trading Estaterooftop solarrooftop solar0.2application submitted may be out of dateupdated Oct 2022Oct 2022—Oct 2022Waverley6.4
St Michaels Abbey, Farnborough Roadsolar farmsolar farm0.2approved, not builtupdated Jun 2026Jan 2026granted Apr 2026Jun 2026Rushmoor7.3
Chancerygate Wayrooftop solarrooftop solar0.3approved, not builtupdated May 2024Mar 2024granted May 2024May 2024Rushmoor8.0
Chancerygate Wayrooftop solarrooftop solar0.3abandonedupdated Feb 2021Jan 2020—Feb 2021Rushmoor8.0
Bartley Wood Business Parkrooftop solarrooftop solar0.1approved, not builtupdated Aug 2023May 2023granted Jul 2023Aug 2023Hart8.1
Chosley Farm, North Warnborough Solar Farm and Battery storagebattery storagebattery storage—approved, not built may be out of dateupdated Feb 2026Jan 2021granted Nov 2021Feb 2026Hart8.6
Contra House, Oak Closerooftop solarrooftop solar0.3application submittedJun 2026——Surrey Heath8.7
Bunkers Hill Farm Solar farm & Battery stationsbattery storagebattery storage—under constructionupdated Nov 2021Feb 2021granted Nov 2021Nov 2021Hart9.1
Gbc Uk, Glebeland Roadrooftop solarrooftop solar0.2application submittedMar 2026——Surrey Heath9.1
Tesco Stores, Marshall Roadrooftop solarrooftop solar0.2approved, not builtupdated Jan 2026Oct 2025granted Dec 2025Jan 2026Bracknell Forest9.3

Distance from the average position of the GU52 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm111531170
Rooftop solar1639125.2
Battery storage110802356

MW in pipeline: pending, approved and under-construction capacity.

How Hart decides solar, wind and battery applications

ApplicationsHartUK
Decided applications (solar, wind, battery)1810,236
Refused5 (28%)19%
Solar refused3 of 1012%
Battery storage refused2 of 816%
Median time from submission to decision34.8 weeks17.0 weeks
Appeals lodged / allowed3 / 1—

All projects in Hart

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near GU52, 9 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.