Crondall Road, Crondall - Fleet Bramley Battery Energy Storage (99.9 MW)

Crondall Road, Crondall - Fleet Bramley Battery Energy Storage is a 99.9 MW battery storage project in Hart, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 22 August 2025, not yet built; the record was last updated on 11 September 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

99.9 MWbattery storage
approved, not builtstatus in REPD
11 September 2025record last updated
Hartcouncil area

Planning timeline

DateStage
9 January 2025Application submitted
22 August 2025Planning permission granted
22 August 2028Permission due to expire (unless work starts)

Project details

Technology
battery storage (stand-alone storage)
Capacity
99.9 MW
Status (REPD)
approved, not built
Record last updated
11 September 2025
Operator or applicant
Cragside Energy Limited
Planning authority
Hart
Planning application reference
24/02491/FUL
Address (REPD)
West Side Of Crondall Road, Crondall, Farnham
Council area (by location)
Hart
Time to decision
32 weeks
REPD reference
16472

Who decides

ApplicationsHartUK
Decided applications (solar, wind, battery)1810,236
Refused5 (28%)19%
Solar refused3 of 1012%
Battery storage refused2 of 816%
Median time from submission to decision34.8 weeks17.0 weeks
Appeals lodged / allowed3 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Bowenhurst Farm, Mill Lanebattery storage100refused0.8
Blue Bell Lodge, Rye Common Lanebattery storage49.5approved, not built0.9
Rye Commonbattery storage49.5approved, not built1.0
Fleet Substationbattery storage49.9application withdrawn1.3
Coxmoor Wood, Crondall Roadbattery storage57approved, not built1.5
Penn Croft Farm, Crondallbattery storage100approved, not built2.4
Hungerford Farmsolar farm5operational3.7
Taplins Farm solar parksolar farm5.9operational4.7
Marsh House Solar Parksolar farm5.5operational4.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.2483, -0.862).