Energy Projects Near You

Marsh House Solar Park (5.5 MW)

Marsh House Solar Park is a 5.5 MW solar farm project in East Hampshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 21 March 2015; the record was last updated on 14 April 2015.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5.5 MWsolar farm
operationalstatus in REPD
14 April 2015record last updated
East Hampshirecouncil area

Planning timeline

DateStage
6 March 2012Application submitted
28 August 2012Refused by the planning authority
23 December 2013Planning permission granted
23 December 2013Appeal allowed
6 June 2014Construction started
21 March 2015Operational

Project details

Technology
solar farm
Capacity
5.5 MW
Status (REPD)
operational
Record last updated
14 April 2015
Operator or applicant
Constantine Land Ltd
Planning authority
East Hampshire
Planning application reference
53234/001
Appeal reference
A/13/2189797/NWF
Site area
12.3 ha
Address (REPD)
Ne/O Gully Copse, Cheeks Farm Lane, Bentley, Alton, Hampshire
Council area (by location)
East Hampshire
Time to decision
94 weeks
REPD reference
1233

Who decides

ApplicationsEast HampshireUK
Decided applications (solar, wind, battery)1910,236
Refused4 (21%)19%
Solar refused2 of 1612%
Battery storage refused2 of 316%
Median time from submission to decision13.0 weeks17.0 weeks
Appeals lodged / allowed0 / 2—

Other large projects within 10 km

ProjectTypeMWStatuskm
Penn Croft Farm, Crondallbattery storage100approved, not built4.6
Crondall Road, Crondall - Fleet Bramley Battery Energy Storagebattery storage99.9approved, not built4.8
Bowenhurst Farm, Mill Lanebattery storage100refused4.9
Rye Commonbattery storage49.5approved, not built5.1
Blue Bell Lodge, Rye Common Lanebattery storage49.5approved, not built5.3
Fleet Substationbattery storage49.9application withdrawn5.6
Fleet Hill Solar Farmsolar farm47.5under construction6.2
Coxmoor Wood, Crondall Roadbattery storage57approved, not built6.3
Land east of Kingsley Sports Clubsolar5permission expired7.4

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.2056, -0.8486).