Penn Croft Farm, Crondall (100 MW battery storage)

Penn Croft Farm, Crondall is a 100 MW battery storage project in Hart, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 30 January 2023, not yet built; the record was last updated on 24 December 2021. REPD also records that the planning permission expired on 30 January 2026, so the project may not go ahead in this form. Check the planning authority's register for the latest position.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

100 MWbattery storage
approved, not builtmay be out of datestatus in REPD
24 December 2021record last updated
Hartcouncil area

REPD also records that the planning permission expired on 30 January 2026, so the project may not go ahead in this form.

Planning timeline

DateStage
16 December 2021Application submitted
30 January 2023Planning permission granted
30 January 2026Permission expired

Project details

Technology
battery storage (stand-alone storage)
Capacity
100 MW
Status (REPD)
approved, not built
Record last updated
24 December 2021
Operator or applicant
Fleet BESS Limited & SSE Energy Solutions Limited
Planning authority
Hart
Planning application reference
21/02937/FUL
Address (REPD)
Penn Croft Farm Penn Croft Crondall Farnham
Council area (by location)
Hart
Time to decision
59 weeks
Name in REPD
Penn Croft Farm, Crondall - Battery Energy Storage Facility
REPD reference
10163

Who decides

ApplicationsHartUK
Decided applications (solar, wind, battery)1810,236
Refused5 (28%)19%
Solar refused3 of 1012%
Battery storage refused2 of 816%
Median time from submission to decision34.8 weeks17.0 weeks
Appeals lodged / allowed3 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Rye Commonbattery storage49.5approved, not built1.6
Bowenhurst Farm, Mill Lanebattery storage100refused1.6
Blue Bell Lodge, Rye Common Lanebattery storage49.5approved, not built1.8
Fleet Substationbattery storage49.9application withdrawn1.8
Crondall Road, Crondall - Fleet Bramley Battery Energy Storagebattery storage99.9approved, not built2.4
Coxmoor Wood, Crondall Roadbattery storage57approved, not built3.2
Fleet Hill Solar Farmsolar farm47.5under construction3.4
Marsh House Solar Parksolar farm5.5operational4.6
Hungerford Farmsolar farm5operational4.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.2372, -0.891).