Energy Projects Near You

Solar, wind and battery projects near Hook (RG29)

26 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of RG29 (Hart): 3 are waiting for a planning decision, 15 approved but not yet running, 4 operational. The largest live scheme is Penn Croft Farm, Crondall (100 MW battery storage, approved on 30 January 2023, not yet built; REPD status may be out of date), 4.0 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

26projects within 10 km
3awaiting a decision
15approved, not running
4operational

Projects within 10 km of RG29

Projects of 1 MW and more (19)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Chosley Farm, North Warnborough Solar Farm and Battery storagesolar farmsolar farm49.9approved, not built may be out of dateupdated Feb 2026Jan 2021granted Nov 2021Feb 2026Hart1.0
Fleet Hill Solar Farmsolar farmsolar farm47.5under constructionupdated Jun 2026Jan 2024granted Apr 2025Jun 2026Hart2.7
Potbridge Farmsolar farmsolar farm4appeal withdrawnupdated Jul 2016Jul 2015refused Oct 2015Jul 2016Hart3.6
Penn Croft Farm, Crondallbattery storagebattery storage100approved, not built may be out of dateupdated Dec 2021Dec 2021granted Jan 2023Dec 2021Hart4.0
Trimmers Solar Farmsolar farmsolar farm10refused on appealupdated May 2016Aug 2015refused Nov 2015May 2016Hart4.2
Holt Lane Solar Parksolar farmsolar farm22application submittedupdated Jun 2025May 2025—Jun 2025Hart4.6
Fleet Substationbattery storagebattery storage49.9application withdrawnupdated Dec 2019Jun 2019—Dec 2019Hart4.6
Rye Commonbattery storagebattery storage49.5approved, not built may be out of dateupdated Mar 2020Mar 2020granted Sep 2021Mar 2020Hart4.8
Blue Bell Lodge, Rye Common Lanebattery storagebattery storage49.5approved, not built may be out of dateupdated Sep 2023Jan 2023granted May 2023Sep 2023Hart5.0
Bowenhurst Farm, Mill Lanebattery storagebattery storage100refusedupdated Apr 2026Jul 2025refused Feb 2026Apr 2026Hart5.1
Coxmoor Wood, Crondall Roadbattery storagebattery storage57approved, not builtupdated May 2024Apr 2023granted Apr 2024May 2024Hart5.8
Crondall Road, Crondall - Fleet Bramley Battery Energy Storagebattery storagebattery storage99.9approved, not builtupdated Sep 2025Jan 2025granted Aug 2025Sep 2025Hart5.9
Hungerford Farmsolar farmsolar farm5operationalupdated Oct 2016Jul 2015granted Oct 2015Oct 2016Hart5.9
Bunkers Hill Farm Solar farm & Battery stationssolar farmsolar farm49.9under constructionupdated Jan 2022Feb 2021granted Nov 2021Jan 2022Hart6.0
Taplins Farm solar parksolar farmsolar farm5.9operationalupdated Jul 2016May 2014granted Oct 2014Jul 2016Hart6.4
Marsh House Solar Parksolar farmsolar farm5.5operationalupdated Apr 2015Mar 2012granted Dec 2013Apr 2015East Hampshire8.1
Basing Roadbattery storagebattery storage20application submitted may be out of dateupdated Feb 2023Jul 2021—Feb 2023Basingstoke and Deane8.5
Kiln Fields Solar Farmsolar farmsolar farm17.9under constructionupdated Jan 2024Nov 2021granted Dec 2021Jan 2024Hart9.2
Frying Down Copse Solar Farmsolar farmsolar farm5operationalupdated Oct 2012Feb 2011granted May 2011Oct 2012Basingstoke and Deane9.3
Smaller schemes under 1 MW, mostly rooftop solar (7)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Chosley Farm, North Warnborough Solar Farm and Battery storagebattery storagebattery storage—approved, not built may be out of dateupdated Feb 2026Jan 2021granted Nov 2021Feb 2026Hart1.0
Bartley Wood Business Parkrooftop solarrooftop solar0.1approved, not builtupdated Aug 2023May 2023granted Jul 2023Aug 2023Hart3.8
Bunkers Hill Farm Solar farm & Battery stationsbattery storagebattery storage—under constructionupdated Nov 2021Feb 2021granted Nov 2021Nov 2021Hart6.0
Little Willow, Upper Anstey Lanesolar farmsolar farm0.4approved, not builtupdated Apr 2026Jan 2025granted Feb 2026Apr 2026East Hampshire8.8
The Costello Schoolrooftop solarrooftop solar—approved, not builtupdated Nov 2025Jul 2025granted Oct 2025Nov 2025Basingstoke and Deane9.4
Steyne Farmsolar farmsolar farm—application submitted may be out of dateupdated Mar 2021Jan 2021—Mar 2021East Hampshire9.6
Pinewood, Crockford Lanesolar farmsolar farm0.2approved, not builtupdated Feb 2024Dec 2023granted Feb 2024Feb 2024Basingstoke and Deane10.0

Distance from the average position of the RG29 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm142641188
Rooftop solar202000.1
Battery storage101701376

MW in pipeline: pending, approved and under-construction capacity.

How Hart decides solar, wind and battery applications

ApplicationsHartUK
Decided applications (solar, wind, battery)1810,236
Refused5 (28%)19%
Solar refused3 of 1012%
Battery storage refused2 of 816%
Median time from submission to decision34.8 weeks17.0 weeks
Appeals lodged / allowed3 / 1—

All projects in Hart

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near RG29, 7 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.