Trimmers Solar Farm (10 MW)
Trimmers Solar Farm is a 10 MW solar farm project in Hart, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on appeal on 26 April 2016; the record was last updated on 4 May 2016.
10 MWsolar farm
refused on appealstatus in REPD
4 May 2016record last updated
Hartcouncil area
Planning timeline
| Date | Stage |
|---|---|
| 17 August 2015 | Application submitted |
| 16 November 2015 | Refused by the planning authority |
| 15 December 2015 | Appeal lodged |
| 26 April 2016 | Appeal refused |
Project details
- Technology
- solar farm
- Capacity
- 10 MW
- Status (REPD)
- refused on appeal
- Record last updated
- 4 May 2016
- Operator or applicant
- Trimmers Solar Farm
- Planning authority
- Hart
- Planning application reference
- 15/01614/FUL
- Appeal reference
- APP/N1730/W/15/3139981
- Site area
- 17.9 ha
- Address (REPD)
- Trimmers Farm, Totters Lane, Hartley Wintney, Hook
- Council area (by location)
- Hart
- Time to decision
- 13 weeks
- REPD reference
- 5706
Who decides
| Applications | Hart | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 18 | 10,236 |
| Refused | 5 (28%) | 19% |
| Solar refused | 3 of 10 | 12% |
| Battery storage refused | 2 of 8 | 16% |
| Median time from submission to decision | 34.8 weeks | 17.0 weeks |
| Appeals lodged / allowed | 3 / 1 | — |
Other large projects within 10 km
| Project | Type | MW | Status | km |
|---|---|---|---|---|
| Holt Lane Solar Park | solar farm | 22 | application submitted | 1.5 |
| Bunkers Hill Farm Solar farm & Battery stations | solar farm | 49.9 | under construction | 2.8 |
| Taplins Farm solar park | solar farm | 5.9 | operational | 3.1 |
| Hungerford Farm | solar farm | 5 | operational | 3.2 |
| Chosley Farm, North Warnborough Solar Farm and Battery storage | solar farm | 49.9 | approved, not built | 4.5 |
| Fleet Substation | battery storage | 49.9 | application withdrawn | 4.6 |
| Coxmoor Wood, Crondall Road | battery storage | 57 | approved, not built | 4.8 |
| Blue Bell Lodge, Rye Common Lane | battery storage | 49.5 | approved, not built | 5.1 |
| Rye Common | battery storage | 49.5 | approved, not built | 5.1 |
Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.2818, -0.9268).